FIR16-00670
| INSP-Sprinkler Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 2:52:35 PM | P | PASS |
|
|
See the city approved plans for locations of piping inspected and where piping is ok to cover.
|
BLD16-02737
| FIRE-Final Inspection | 11/17/2016 | 11/17/2016 | 11/17/2016 2:13:40 PM | P | PASS |
|
|
Life safety passed. I noted to the contractor that the building inspector would probably take exception to the existing thumbturn dead bolt on the kitchen doors.
|
BLD14-03070
| FIRE-Final Inspection | 11/16/2016 | 11/17/2016 | 11/17/2016 2:12:09 PM | A | FAIL |
|
|
Need the project related fire sprinkler and and fire alarm permits addressed prior to an inspection.
|
FIR16-00364
| INSP-Final Inspection | 11/16/2016 | 11/17/2016 | 11/17/2016 2:11:35 PM | A | FAIL |
|
|
Contractor did not arrive for inspection. I notified them that the plan changes still had not been addressed as noted in a previous inspection
|
FIR16-00254
| INSP-Final Inspection | 11/15/2016 | 11/17/2016 | 11/17/2016 2:10:13 PM | A | FAIL |
|
|
Could not test the alarms due to the sprinkler contractor not being there. Will need to reschedule.
|
BLD16-03080
| FIRE-Final Inspection | 11/17/2016 | 11/17/2016 | 11/17/2016 1:26:14 PM | P | PASS |
|
|
life safety passed
|
BLD16-03146
| FIRE-Final Inspection | 11/17/2016 | 11/17/2016 | 11/17/2016 1:25:09 PM | P | PASS |
|
|
Life safety passed
|
BLD16-02193
| FIRE-Final Inspection | 11/16/2016 | 11/17/2016 | 11/17/2016 11:34:44 AM | A | FAIL |
|
|
Provide small documents/notes, provide ADA compliant hardware (see door schedule) contact plan review about deadbolt on door between tenants.
|
FIR16-00357
| INSP-Alarm Testing | 11/16/2016 | 11/17/2016 | 11/17/2016 9:27:09 AM | A | PART |
|
|
New notification devices functioned correctly in the new scope of work. The issues is the new devices do not sync with the existing devices outside of the scope of work. I contacted Ron with the Boise Fire Dept and he stated that the new and old devices will need to sync as per code requirements.
|