Inspections for the day of: Wednesday, November 18, 2009.
Number of inspections: 8
Percentage of inspections complete: 88 %
Percentage of inspections not complete: 13 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00518 INSP-Conference11/13/200911/16/2009 P 
KEN Phone #: ###-#### (Follow up with Jerry McAdams)
FIR09-00489 FIR-Aging Inspection11/18/200911/18/200911/19/2009 8:28:45 AM NR
work is in progress
BLD09-01819 FIRE-Conference11/18/200911/18/200911/18/2009 4:11:41 PMPDONE
Went over life safety requirements with Bill and discussed a fire watch, which I deferred to Mark Senteno. Owner stated he is going to open this Thursday night for a VIP party. I notified him of possible consequences. I notified Mark Senteno of this as well.
FIR09-00616 INSP-Final Inspection11/18/200911/18/200911/18/2009 4:09:52 PMPFAIL
No city approved plans on site. But Tim and I noted some pendant heads less than 6' apart. I notified Bill Matter of this.
FIR09-00347 INSP-Supply line flush11/17/200911/18/200911/18/2009 4:08:49 PMAPASS
Underground supply line flush passed
FIR09-00186 INSP-Sprinkler Rough-in/Hydro11/16/200911/18/200911/18/2009 4:08:04 PMAPASS
Underground hydro test passed
BLD09-01960 FIRE-Final Inspection11/17/200911/18/200911/18/2009 8:08:38 AMAPASS
Life safety passed.
BLD09-01946 FIRE-Final Inspection11/17/200911/18/200911/17/2009 2:29:33 PMAPASS
Life safety passed. The floor plan has been revised and approved by Carl.