Inspections for the day of: Monday, November 18, 2019.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJack Reynolds
TitleMEC INSPECTOR
Phone #208-803-2395
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC19-00118 Final11/18/201911/18/201911/18/2019 4:19:19 PMPPASS
Please call installer when you are on your way at ###-#### and call Ryan with questions at ###-####. Thank you Phone #: ###-#### Inspection requested via web by Rhonda Marcum
- final ok
MEC19-04449 Final11/14/201911/18/201911/18/2019 3:45:54 PMPPASS
If able call client prior to arrival at ###-#### Phone #: ###-#### Inspection requested via web by Andrea Grigsby
- furnace ac coil co ok
MEC19-03013 Pressure Test11/18/201911/18/201911/18/2019 3:18:35 PMPFAIL
Mark Phone #: ###-####
- need 30lb gauge for 20lb gas test
MEC19-05090 Final11/12/201911/18/201911/18/2019 2:58:28 PMPFAIL
Phone #: ###-#### Inspection requested via web by Mary LaFayette
- furnace needs service disconnect in mech room
MEC19-05203 Final11/15/201911/18/201911/18/2019 2:30:47 PMPNR
Please call Dan on your way - ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks
MEC19-04982 Final11/12/201911/18/201911/18/2019 2:28:14 PMPPASS
Please call 30 minutes prior to arriving. Phone #: ###-#### Inspection requested via web by Michele Johnson
- air handler ac coil final ok
MEC19-05191 Final11/15/201911/18/201911/18/2019 1:51:07 PMPPASS
INSTALLER JAROD ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
- furnace ac coil co ok
MEC19-05163 DOC - Permit Finaled11/18/201911/18/201911/18/2019 1:29:10 PMPPASS
final ok
MEC19-05163 Pressure Test11/15/201911/18/201911/18/2019 1:28:48 PMPPASS
Field super: Jason Shipp Phone #: ###-#### Inspection requested via web by Lisa Whitney
- 20lb gas pressure test ok
- final ok
MEC19-03990 Rough-in11/18/201911/18/201911/18/2019 12:07:09 PMPPASS
cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen
- 1st floor ceiling cover ok
MEC19-02222 Final11/15/201911/18/201911/18/2019 12:05:04 PMAPART
if questions call Efrain @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
- partial final 1st floor ceiling cover ok
MEC19-05202 Pressure Test11/15/201911/18/201911/18/2019 12:03:28 PMAPASS
Phone #: ###-#### Inspection requested via web by Devry King
- 20lb gas pressure test ok
- CSST needs supported in crawl for final
MEC19-04780 Final11/15/201911/18/201911/18/2019 10:33:45 AMAPASS
call ahead to Chris @ ###-#### to make sure he can be home for inspector entry. Phone #: ###-#### Phone #: ###-#### Inspection requested via web by Angie Maguire
- final ok
MEC19-00118 Final11/14/201911/18/201911/18/2019 10:10:53 AMAFAIL
After 9 requested by contractor, please call him 30 minutes in advance for access at ###-#### and call Ryan with any questions at ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum
- both water heater and furnace flues have combustible materials within 1"
- secondary drain penetrations needs sealed
MEC19-02427 Final11/15/201911/18/201911/18/2019 9:43:12 AMAPASS
Please Call Kyle at ###-#### when on the way so that Kyle Korb can meet the inspector on site. Phone #: ###-#### Inspection requested via web by Ashley Shoecraft
- wall had to be cut open to access fireplace flue
- vapor barrier needed cut back on bottom side and two sets of prints removed from fireplace cavity.
- fireplace final ok
MEC19-01831 Mec-Aging Inspection11/18/201911/18/201911/18/2019 8:05:19 AM FAIL
Schedule inspection with homwowner if work is finished. On 5-15-19 work wasn't ready for inspection.