Inspections for the day of: Monday, November 19, 2001.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR01-00455 FIR-Aging Inspection11/19/200111/19/200111/19/2001 12:00:00 AM PASS
work is complete. No permit card on site to sign. 11/19/2001 10:39:15 AM
FIR01-00521 INSP-Sprinkler Rough-in11/19/200111/19/200111/19/2001 12:00:00 AMAPASS
Added by Inspector: 430 On 11/19/2001 9:03:21 AM Sprinkler rough-in OK
FIR01-00521 INSP-Sprinkler Rough-in/Hydro11/19/200111/19/200111/19/2001 12:00:00 AMAPASS
Added by Inspector: 430 On 11/19/2001 10:54:05 AM Above ground hydro test OK.
FIR01-00521 INSP-Supply line flush11/16/200111/19/200111/19/2001 12:00:00 AMAPASS
Supply line flush OK. 11/19/2001 9:02:24 AM
FIR01-00386 INSP-Sprinkler Rough-in/Hydro11/16/200111/19/200111/19/2001 12:00:00 AMAPASS
Above ground hydro test OK 11/20/2001 12:50:32 PM
BLD01-00309 FIRE-Final Inspection11/16/200111/19/200111/19/2001 12:00:00 AMAPASS
Fire alarm, fire sprinklers and life/safety OK. OK for perm occ. 11/19/2001 7:44:59 AM
BLD01-00017 FIRE-Final Inspection11/16/200111/19/200111/19/2001 12:00:00 AMPPASS
OK for perm occ 11/20/2001 3:07:04 PM
BLD01-00016 FIRE-Final Inspection11/16/200111/19/200111/19/2001 12:00:00 AMPPASS
OK for perm occ 11/20/2001 3:07:27 PM
BLD01-00012 FIRE-Final Inspection11/16/200111/19/200111/19/2001 12:00:00 AMPPASS
OK for perm occ 11/20/2001 3:07:58 PM
FIR01-00503 INSP-Alarm Testing11/15/200111/19/200111/19/2001 12:00:00 AMPPASS
Fire alarm work finaled. 11/19/2001 1:37:30 PM
FIR01-00502 INSP-Alarm Testing11/15/200111/19/200111/19/2001 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 11/15/2001 at 12:24:19. Contact: ###-####. Fire alarm work finaled. 11/19/2001 1:37:11 PM