FIR11-00431
| INSP-Final Inspection | 11/19/2012 | 11/19/2012 | 11/19/2012 5:04:09 PM | P | PART |
|
|
All modifications to the original design to be shown on as-built drawings including additional heads under ductwork at the dock area. Remainder of revisions are acceptable.
|
BLD12-01789
| FIRE-Final Inspection | 11/19/2012 | 11/19/2012 | 11/19/2012 4:57:30 PM | P | PASS |
|
|
Fire life safety and project related alarm work okay for final per T. Cobbley.
|
FIR11-00645
| INSP-Final Inspection | 11/19/2012 | 11/19/2012 | 11/19/2012 4:55:43 PM | P | PASS |
|
|
Field verified as-built drawings. Permit finaled.
|
FIR12-00624
| INSP-Sprinkler Rough-in | 11/19/2012 | 11/19/2012 | 11/19/2012 1:33:50 PM | A | NR |
|
|
|
BLD12-01742
| FIRE-Conference | 11/19/2012 | 11/19/2012 | 11/19/2012 1:31:11 PM | P | DONE |
|
|
Regarding fire alarm permit work.
|
BLD12-01681
| FIRE-Sprinkler Rough-in | 11/19/2012 | 11/19/2012 | 11/19/2012 1:29:49 PM | A | PART |
|
|
Ref. stamped fire sprinkler plans for overhead work approved to date.
|
BLD12-02086
| FIRE-Final Inspection | 11/19/2012 | 11/19/2012 | 11/19/2012 12:01:58 PM | A | PART |
|
|
Project related fire alarm and fire sprinkler permits passed final inspections. Provide approved plans on site for fire life safety walkthrough.
|
FIR12-00246
| INSP-Sprinkler Rough-in | 11/19/2012 | 11/19/2012 | 11/19/2012 11:59:34 AM | A | PART |
|
|
Okay to cover hard lid ceilings at the common areas west wing.
|