GCB13-00092
| GCB-Framing | 11/18/2013 | 11/19/2013 | 11/19/2013 2:16:04 PM | P | NR |
|
|
Bob ###-####. Needs other trades first.
|
BLD13-00888
| BLD-Final | 11/19/2013 | 11/19/2013 | 11/19/2013 1:47:21 PM | P | PART |
|
|
Troy Phone #: ###-####. All missing ADA restroom componets installed. Still need final letter from special inspection agency.
|
BLD13-02050
| BLD-Framing/Rough-in | 11/18/2013 | 11/19/2013 | 11/19/2013 11:04:50 AM | A | PART |
|
|
Call brian prior Phone #: ###-#### >> Inspection requested via web by Brian Stark. ok to insulate. needs to provide truss engineering and install holdowns on interior shear walls.
|
BLD13-01539
| BLD-Footing | 11/18/2013 | 11/19/2013 | 11/19/2013 9:42:58 AM | A | PASS |
|
|
CHARLES - REBAR Phone #: ###-####. Rebar for light weight concrete placement on roof deck of patient addition phase 1A.
|
BLD13-01539
| BLD-Framing/Rough-in | 11/19/2013 | 11/19/2013 | 11/19/2013 9:41:21 AM | A | PASS |
|
|
CHARLES - Phone #: ###-####. INterior steel steud partition wall for xray room C135, phase 1B. Structural steel beam to column connections, roof decking as per approved plans. All special inspections for complete joint penetration welds, fillet welds puddle welds and nelson studs ok, for patient phase 1A patient addition.
|