Inspections for the day of: Tuesday, November 19, 2013.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
GCB13-00092 GCB-Framing11/18/201311/19/201311/19/2013 2:16:04 PMPNR
Bob ###-####. Needs other trades first.
BLD13-00888 BLD-Final11/19/201311/19/201311/19/2013 1:47:21 PMPPART
Troy Phone #: ###-####. All missing ADA restroom componets installed. Still need final letter from special inspection agency.
BLD13-02050 BLD-Framing/Rough-in11/18/201311/19/201311/19/2013 11:04:50 AMAPART
Call brian prior Phone #: ###-#### >> Inspection requested via web by Brian Stark. ok to insulate. needs to provide truss engineering and install holdowns on interior shear walls.
BLD13-01539 BLD-Footing11/18/201311/19/201311/19/2013 9:42:58 AMAPASS
CHARLES - REBAR Phone #: ###-####. Rebar for light weight concrete placement on roof deck of patient addition phase 1A.
BLD13-01539 BLD-Framing/Rough-in11/19/201311/19/201311/19/2013 9:41:21 AMAPASS
CHARLES - Phone #: ###-####. INterior steel steud partition wall for xray room C135, phase 1B. Structural steel beam to column connections, roof decking as per approved plans. All special inspections for complete joint penetration welds, fillet welds puddle welds and nelson studs ok, for patient phase 1A patient addition.