BLD18-02216
| BLD-Final | 11/18/2019 | 11/19/2019 | 11/21/2019 7:58:35 AM | A | PASS |
|
|
windows in back - dog in backyard - home at 4:20 // Emily Phone #: ###-####
|
BLD19-04501
| BLD-Final | 11/18/2019 | 11/19/2019 | 11/19/2019 3:42:21 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Elizabeth Melendez//roof appears to be installed within code requirements//
|
BLD19-04501
| DOC - Permit Finaled | 11/19/2019 | 11/19/2019 | 11/19/2019 3:41:51 PM | P | PASS |
|
|
|
BLD18-03667
| BLD-Final | 11/19/2019 | 11/19/2019 | 11/19/2019 3:41:38 PM | P | NR |
|
|
Bob Phone #: ###-####//need to modify hand rail to meet plan mod//discussed onsite//
|
BLD19-00323
| BLD-Wall Bracing | 11/19/2019 | 11/19/2019 | 11/19/2019 1:28:42 PM | P | CANC |
|
|
call for keycode access // Kim Phone #: ###-####//CN posted still needs completed//updated engineering needed to reflect what was performed onsite that does not reflect the approved truss fixes//no wall bracing inspection needed at this time//
|
BLD19-00326
| BLD-Wall Bracing | 11/19/2019 | 11/19/2019 | 11/19/2019 1:27:24 PM | P | CANC |
|
|
call for keycode access // Kim Phone #: ###-####//CN still onsite--corrections have not been completed//updated engineering will be needed to reflect what has been completed onsite--see correction notice//no wall bracing inspection needed at this time//
|
BLD19-00533
| BLD-Concrete | 11/18/2019 | 11/19/2019 | 11/19/2019 12:58:20 PM | P | PASS |
|
|
The walls for building J are getting poured Wednesday about noon Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials and rebar clearances//
|
BLD18-02261
| BLD-Final | 11/18/2019 | 11/19/2019 | 11/19/2019 11:40:28 AM | A | CANC |
|
|
Jeff Phone #: ###-####//need fire life safety//let Jeff know and he will reschedule//
|
BLD19-00553
| BLD-Conference | 11/12/2019 | 11/19/2019 | 11/19/2019 10:53:43 AM | A | DONE |
|
|
follow up on CN for pole structure....//stopped by, no progress on pole structure..//
|
BLD19-03775
| BLD-Framing/Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 10:32:27 AM | A | PART |
|
|
Phone #: 2089419532 >> Inspection requested via mobile web by Ren Tracy//add trough bolts for knee brace or equivilant per plans//have engineer approval of post base used in place of detailed base//will be visible at final//
|
BLD19-00680
| BLD-Final | 11/18/2019 | 11/19/2019 | 11/19/2019 10:04:54 AM | A | PASS |
|
|
John Phone #: ###-####//final complete per plans//ok once CDHD has signed off//
|
BLD19-03532
| BLD-Framing/Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 9:15:22 AM | A | FAIL |
|
|
Ed Phone #: ###-####//need to add nails for shear or provide staple conversion per engineer//add A35s per notes by engineer//
|
MIS18-00406
| MIS-Aging Inspection | 11/19/2019 | 11/19/2019 | 11/19/2019 8:58:45 AM | | CANC |
|
|
|
MIS18-00402
| MIS-Aging Inspection | 11/19/2019 | 11/19/2019 | 11/19/2019 8:57:29 AM | | DONE |
|
|
ESC ok per notes below
|
MIS18-00402
| DOC - Permit Finaled | 11/19/2019 | 11/19/2019 | 11/19/2019 8:56:53 AM | P | PASS |
|
|
|
BLD19-01380
| BLD-Wall Bracing | 11/18/2019 | 11/19/2019 | 11/19/2019 8:44:58 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Braden Holbrook//corrections made//
|