FIR99-00556
| INSP-Conference | 10/29/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | A | PART |
|
|
###-#### With contractor about addressing; PIV for sprinklers (not installed- will use 1hr room)
|
BLD99-01717
| FIRE-Sprinkler Rough-in | 11/1/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 15:17:41. Contact: ###-####. Supply line cover inspection- ok to cover
|
BLD99-01718
| FIRE-Sprinkler Rough-in | 11/1/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 15:19:48. Contact: ###-####. Supply line cover inspection- ok to cover
|
BLD99-02802
| FIRE-Sprinkler Rough-in | 11/1/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 15:20:32. Contact: ###-####. Supply line cover inspection- ok to cover
|
BLD99-01720
| FIRE-Sprinkler Rough-in | 11/1/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 15:22:12. Contact: ###-####. Supply line cover inspection- ok to cover
|
BLD98-01168
| FIRE-Conference | 11/1/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 16:01:48. Contact: ###-####. With simplea and contractor to review fire alarm plans.
|
FIR99-00556
| INSP-Sprinkler Rough-in | 11/2/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | A | FAIL |
|
|
hangers no installed at end of pipe in all areas. Spacing of hagers at elbows incorrect.
|
BLD99-00184
| FIRE-Final Inspection | 11/2/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | P | PASS |
|
|
Occ. appr.
|
BLD99-02289
| FIRE-Final Inspection | 11/1/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | P | PASS |
|
|
JAY ###-#### Occ. Approved
|
BLD99-01486
| FIRE-Final Inspection | 11/2/1999 | 11/2/1999 | 11/2/1999 12:00:00 AM | P | PART |
|
|
JAY ###-#### Assembly permit reqired.
|