PLM01-02279
| PLM-Aging Inspection | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | | PART |
|
|
90 more 11/2/2001 8:54:35 AM
|
PLM01-02623
| PLM-Aging Inspection | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | | FAIL |
|
|
called, contractor never called back. 11/2/2001 12:46:44 PM
|
PLM01-03240
| Groundwork | 11/1/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/01/2001 at 10:47:28. Contact: ###-####.
|
PLM01-03009
| Final | 11/1/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/01/2001 at 14:50:13. Contact: ###-####.
|
PLM01-03009
| Final | 11/1/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/01/2001 at 14:50:13. Contact: ###-####.
|
PLM01-03761
| Water and/or Sewer | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | A | PART |
|
|
###-#### JEFF They wern't ready and soundeded like they had questions so I stopped by and lined them out on a tee for the vent off of the interceptor, testing the tank and installing the proper fittings for more than a 45 degree change of direction horizontally. 11/2/2001 2:46:02 PM
|
PLM01-03734
| Sprinkler (Final) | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-#### GREG
|
PLM01-03734
| Sprinkler (Final) | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-#### GREG
|
PLM01-03735
| Sprinkler (Final) | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-#### GREG
|
PLM01-03735
| Sprinkler (Final) | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-#### GREG
|
PLM01-03745
| Sprinkler (Final) | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-#### GREG
|
PLM01-03745
| Sprinkler (Final) | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-#### GREG
|
PLM01-02564
| Plumbing Rough-in | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM01-03744
| Final | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 11/02/2001 at 07:51:11. Contact: ###-####.will reshedule for bv. for tuesday. 11/2/2001 2:46:53 PM
|
PLM01-03760
| Water and/or Sewer | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-#### ROB
|
PLM01-03760
| Water and/or Sewer | 11/2/2001 | 11/2/2001 | 11/2/2001 12:00:00 AM | P | PASS |
|
|
###-#### ROB
|