PLM06-03735
| Final | 11/2/2006 | 11/2/2006 | 11/3/2006 4:39:55 PM | P | PASS |
|
|
lee has talked to Eric from A1 Quality Plumbing regarding this situation//Eric ###-####-a-1 will finish work.
|
PLM06-03412
| Groundwork | 11/2/2006 | 11/2/2006 | 11/2/2006 4:15:00 PM | P | PART |
|
|
Scheduled by a contractor via Hello! on 11/2/2006 at 8:46:30 AM. Contact: ###-####.3x6 iw at grid 7 through area a.
|
PLM06-03728
| Water and/or Sewer | 11/2/2006 | 11/2/2006 | 11/2/2006 3:20:22 PM | P | PASS |
|
|
swr line only --steve ###-####
|
PLM06-03728
| Water and/or Sewer | 11/2/2006 | 11/2/2006 | 11/2/2006 3:20:13 PM | P | PASS |
|
|
swr line only --steve ###-####
|
PLM06-03243
| Groundwork | 11/1/2006 | 11/2/2006 | 11/2/2006 2:34:08 PM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Penny Smith
|
PLM06-02867
| Other | 11/2/2006 | 11/2/2006 | 11/2/2006 2:00:41 PM | P | PART |
|
|
conferance on upgrades for health hazards.need rpbp on coffee maker-need dbcv on 2 ice makers-need to raise vacuum breaker for soap dispenser-need to reroute drains on equipment to an approved air gap-need to upgrade soap dispenser in kitchen or install rpbp.
|
PLM06-03619
| Water and/or Sewer | 11/2/2006 | 11/2/2006 | 11/2/2006 11:03:11 AM | A | PART |
|
|
sewer lines to lift station ok
|
PLM06-03698
| Water and/or Sewer | 11/1/2006 | 11/2/2006 | 11/2/2006 10:56:06 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/1/2006 at 8:43:03 PM. Contact: ###-####.
|
PLM06-03698
| Water and/or Sewer | 11/2/2006 | 11/2/2006 | 11/2/2006 10:55:18 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 11/1/2006 at 8:43:03 PM. Contact: ###-####.
|
PLM06-03585
| Plumbing Rough-in | 11/1/2006 | 11/2/2006 | 11/2/2006 10:08:22 AM | A | PASS |
|
|
partial rough-in for rebuild, combo for lock box is MJS; Phone #: ###-#### Internet Inspection Request from: Mike Dunson
|
PLM05-02534
| Final | 10/31/2006 | 11/2/2006 | 11/2/2006 9:40:17 AM | A | PASS |
|
|
dave ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
PLM06-02763
| Plumbing Rough-in | 11/1/2006 | 11/2/2006 | 11/2/2006 9:22:55 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 11/1/2006 at 2:46:12 PM. Contact: ###-####.-r/i pass, need r-13 insulation behind shower valve in master bath, will call when completed as per conversation with homeowner.
|
PLM06-03719
| Groundwork | 11/2/2006 | 11/2/2006 | 11/2/2006 8:49:08 AM | A | PASS |
|
|
|
PLM06-03719
| Plumbing Rough-in | 11/1/2006 | 11/2/2006 | 11/2/2006 8:48:50 AM | A | CANC |
|
|
###-#### dennis
|
PLM06-02699
| Final | 11/2/2006 | 11/2/2006 | 11/2/2006 8:35:29 AM | P | PASS |
|
|
rod; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt
|
PLM06-01654
| PLM-Aging Inspection | 11/2/2006 | 11/2/2006 | 11/2/2006 8:14:55 AM | | PASS |
|
|
|
PLM06-01738
| PLM-Aging Inspection | 11/2/2006 | 11/2/2006 | 11/2/2006 7:36:57 AM | | NR |
|
|
wip
|