PLM96-03100
| INSP - Plumbing Rough-in | 11/20/1996 | 11/20/1996 | 11/21/1996 12:00:00 AM | P | FAIL |
|
|
11/20/96 352 - more straps needed on cpvc piping in all areas
|
PLM96-03444
| INSP - Ground work | 11/20/1996 | 11/20/1996 | 11/21/1996 12:00:00 AM | P | FAIL |
|
|
11/20/96 352 - ground work test failed
|
PLM96-02521
| INSP - Plumbing Rough-in | 11/19/1996 | 11/20/1996 | 11/20/1996 12:00:00 AM | A | PASS |
|
|
11/20/96 352 - ROUGH-IN FOR BEAUTY SHOP
|
PLM96-02637
| INSP - Final | 11/20/1996 | 11/20/1996 | 11/20/1996 12:00:00 AM | P | PASS |
|
|
11/20/96 352 -
|
PLM96-02868
| INSP - Final | 11/20/1996 | 11/20/1996 | 11/20/1996 12:00:00 AM | P | PASS |
|
|
|
PLM96-03464
| INSP - Final | 11/19/1996 | 11/20/1996 | 11/20/1996 12:00:00 AM | P | CANC |
|
|
ROUGH IN WAS DONE BY EDIGER PLM. DONE BY JSODEN
|
PLM96-01952
| INSP - Final | 11/20/1996 | 11/20/1996 | 11/20/1996 12:00:00 AM | P | PASS |
|
|
11/20/96 352 -
|