MIS03-00105
| FIR-Final | 11/19/2003 | 11/20/2003 | 11/20/2003 12:00:00 AM | A | FAIL |
|
|
###-#### tom Remove the locking hardware from the gate in the patio area, relocate the occupant load sign from inside to outside for the patio area, provide one additional fire extinguisher at the door out to the patio, provide annual inspection for the fire extinguishers. 11/20/2003 12:22:48 PM
|
BLD03-00748
| FIRE-Final Inspection | 11/19/2003 | 11/20/2003 | 11/20/2003 12:00:00 AM | P | PASS |
|
|
fire life safety finaled 11/20/2003 3:46:42 PM
|
FIR03-00600
| INSP-Sprinkler Rough-in/Hydro | 11/20/2003 | 11/20/2003 | 11/20/2003 12:00:00 AM | P | PART |
|
|
24 hour test begins with 46 lbs at 12:30 11/20/2003 12:31:35 PM
|
FIR03-00081
| INSP-Sprinkler Rough-in/Hydro | 11/20/2003 | 11/20/2003 | 11/20/2003 12:00:00 AM | P | PART |
|
|
sprinkler piping in attic appears to be properly tented. I notified the contractor (Trent Bice) that the insulation would have to be brought up over the tenting and the pipe to prevent freezing 11/20/2003 4:30:58 PM
|
BLD03-01836
| FIRE-Final Inspection | 11/20/2003 | 11/20/2003 | 11/20/2003 12:00:00 AM | P | PASS |
|
|
Structural inspector to verify the removal of the thumbturn from the main exit, provide approved door hardware on the east exit door 11/20/2003 1:07:35 PM
|
FIR03-00555
| INSP-Sprinkler Rough-in/Hydro | 11/20/2003 | 11/20/2003 | 11/20/2003 12:00:00 AM | P | PASS |
|
|
overhead hydro test is ok. Anti-freeze system hydro test is ok 11/20/2003 3:46:12 PM
|