BLD06-01678
| FIRE-Conference | 11/20/2006 | 11/20/2006 | 11/20/2006 5:12:53 PM | P | DONE |
|
|
Confrence to discuss door hardware and project scheduled final completion dates.
|
BLD06-02272
| FIRE-Final Inspection | 11/20/2006 | 11/20/2006 | 11/20/2006 5:11:49 PM | P | FAIL |
|
|
Final pending the project related fire alarm permit inspection which failed.
|
FIR06-00647
| INSP-Alarm Testing | 11/19/2006 | 11/20/2006 | 11/20/2006 5:10:27 PM | P | FAIL |
|
|
Stobe notification devices within the TI space are not in sync with the adjacent common corridor devices that are viewable from the same locations.
|
FIR06-00736
| INSP-Final Inspection | 11/20/2006 | 11/20/2006 | 11/20/2006 2:51:59 PM | P | PASS |
|
|
Fire sprinkler passed final inspection, permit finaled.
|
BLD03-01633
| FIRE-Final Inspection | 11/17/2006 | 11/20/2006 | 11/20/2006 12:45:02 PM | A | NH |
|
|
No access to complete inspeciton.
|
FIR06-00595
| INSP-Alarm Testing | 11/17/2006 | 11/20/2006 | 11/20/2006 11:55:18 AM | A | DEFR |
|
|
don Note: if you cant do 6:30 we can do 5:00 pm; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection to be rescheduled.
|
FIR06-00612
| INSP-Final Inspection | 11/20/2006 | 11/20/2006 | 11/20/2006 11:54:19 AM | P | PASS |
|
|
Fire alarm permit finaled.
|
FIR06-00639
| INSP-Sprinkler Rough-in/Hydro | 11/17/2006 | 11/20/2006 | 11/20/2006 11:53:47 AM | A | FAIL |
|
|
AG hydrostatic test not ready at this time due to system leakage to be repaired today per contractor.
|