FIR09-00518
| INSP-Conference | 11/13/2009 | 11/16/2009 | | P | |
|
|
KEN Phone #: ###-#### (Follow up with Jerry McAdams)
|
FIR09-00656
| INSP-Sprinkler Rough-in | 11/20/2009 | 11/20/2009 | 11/20/2009 3:27:52 PM | P | PASS |
|
|
See the city approved plans for sprinkler piping above the hard lids that is ok to cover.
|
FIR09-00448
| INSP-Sprinkler Rough-in/Hydro | 11/20/2009 | 11/20/2009 | 11/20/2009 2:50:32 PM | P | FAIL |
|
|
Both of the overhead systems failed their hydro tests. I found three different locations where water was leaking out of the system and collecting in the baggies on the sprinkler pendants.
|
FIR09-00600
| INSP-Sprinkler Rough-in/Hydro | 11/19/2009 | 11/20/2009 | 11/20/2009 2:49:09 PM | A | PART |
|
|
I finished the rough-in inspection in the previously locked tenant space. I started the above ground hydro test but Brian called me later and stated that he had lost pressure and we would need to reschedule.
|
BLD09-00258
| FIRE-Final Inspection | 11/20/2009 | 11/20/2009 | 11/20/2009 2:38:32 PM | A | PASS |
|
|
life safety passed
|
BLD09-00251
| FIRE-Final Inspection | 11/20/2009 | 11/20/2009 | 11/20/2009 2:38:02 PM | A | PASS |
|
|
life safety passed
|
BLD09-00257
| FIRE-Final Inspection | 11/20/2009 | 11/20/2009 | 11/20/2009 2:37:37 PM | A | PASS |
|
|
life safety passed
|
BLD09-00254
| FIRE-Final Inspection | 11/20/2009 | 11/20/2009 | 11/20/2009 2:37:20 PM | A | PASS |
|
|
life safety passed
|
BLD09-00253
| FIRE-Final Inspection | 11/19/2009 | 11/20/2009 | 11/20/2009 2:36:52 PM | A | PASS |
|
|
life safety passed
|
BLD09-00255
| FIRE-Final Inspection | 11/20/2009 | 11/20/2009 | 11/20/2009 2:36:26 PM | A | PASS |
|
|
life safety passed
|
BLD09-00256
| FIRE-Final Inspection | 11/20/2009 | 11/20/2009 | 11/20/2009 2:35:56 PM | A | PASS |
|
|
life safety passed
|
BLD09-01919
| FIRE-Final Inspection | 11/19/2009 | 11/20/2009 | 11/20/2009 11:33:25 AM | A | PART |
|
|
A temporary occupancy is given with mark sentenos permission until the single action hardware is installed on the north exit door and the two overspaced sprinkler pendants.
|
BLD09-01819
| FIRE-Final Inspection | 11/19/2009 | 11/20/2009 | 11/20/2009 8:17:16 AM | A | CANC |
|
|
Duplicate inspection
|
BLD09-01839
| FIRE-Final Inspection | 11/19/2009 | 11/20/2009 | 11/20/2009 7:54:09 AM | A | PASS |
|
|
Life safety passed
|
BLD09-01840
| FIRE-Final Inspection | 11/19/2009 | 11/20/2009 | 11/20/2009 7:53:15 AM | A | PASS |
|
|
Life safety passed.
|
FIR09-00616
| INSP-Final Inspection | 11/20/2009 | 11/20/2009 | 11/20/2009 7:52:35 AM | P | PASS |
|
|
Permit finaled
|