BLD14-03366
| FIRE-Final Inspection | 11/17/2014 | 11/18/2014 | | P | |
|
|
Elise// please call 45 min prior Phone #: ###-####
|
FIR14-00540
| INSP-Sprinkler Rough-in | 11/19/2014 | 11/20/2014 | 11/20/2014 2:42:17 PM | P | PASS |
|
|
Rough-in passed. Piping can not be covered until a tenting inspection has passed.
|
BLD14-03388
| FIRE-Final Inspection | 11/19/2014 | 11/20/2014 | 11/20/2014 2:41:31 PM | P | FAIL |
|
|
No access. I spoke to Linda and we are going to reschedule
|
FIR14-00661
| INSP-Final Inspection | 11/19/2014 | 11/20/2014 | 11/20/2014 2:11:13 PM | P | CANC |
|
|
To be canceled per Nathan Price and my discussion due to sync issues between the new and existing horns.
|
FIR14-00822
| INSP-Sprinkler Rough-in | 11/19/2014 | 11/20/2014 | 11/20/2014 1:43:47 PM | A | PASS |
|
|
Rough-in passed. Piping can be covered.
|
BLD14-03411
| FIRE-Final Inspection | 11/19/2014 | 11/20/2014 | 11/20/2014 1:04:59 PM | A | PART |
|
|
A temporary was given for life safety as per the scope of work. Bill claims Tim Woodard is ok with existing walls that are not shown on plans. I could not contact Tim. Bill shall provide verification to Building inspector of said conversation prior to a final sign off.
|
FIR14-00835
| INSP-Sprinkler Rough-in | 11/19/2014 | 11/20/2014 | 11/20/2014 12:16:10 PM | A | CANC |
|
|
Cancel per Justin and mine discussion. Phone #: ###-####
|
FIR14-00735
| INSP-Sprinkler Rough-in | 11/19/2014 | 11/20/2014 | 11/20/2014 12:15:36 PM | A | FAIL |
|
|
This was for Bldg D dry system. Heads overspaced, additional fittings and heads blocked by obstructions. Plans need to be resubmitted that match the actual layout. No piping to be covered. Only inspected area at remote area. Did not look at hangers, bracing or restraints.
|
BLD14-02357
| FIRE-Final Inspection | 11/19/2014 | 11/20/2014 | 11/20/2014 10:18:17 AM | A | PASS |
|
|
life safety passed
|
FIR14-00679
| INSP-Final Inspection | 11/19/2014 | 11/20/2014 | 11/20/2014 9:26:03 AM | A | FAIL |
|
|
The new horns in the remodeled area do not sync with the existing horns in the other areas. Also there are exiting smoke detectors, which are over spaced, that are not shown on the city approved plans. A/v's tested ok with the activation of one of the existing smoke detectors. New NAC panel is supervised by the FACP.
|