Inspections for the day of: Wednesday, November 21, 2007.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00865 INSP-Final Inspection11/21/200711/21/200711/21/2007 4:43:43 PMPPASS
permit finaled
BLD07-00712 FIRE-Final Inspection11/20/200711/21/200711/21/2007 3:06:03 PMAFAIL
Repair exit signs, provide emergency lights in the stockroom, provide exit sign at the main exit and provide approved hardware at the main exit.
FIR07-00739 INSP-Sprinkler Rough-in/Hydro11/21/200711/21/200711/21/2007 3:01:22 PMPPASS
Above ground hydro test passed.
BLD07-02297 FIRE-Final Inspection11/20/200711/21/200711/21/2007 3:00:39 PMAFAIL
Per the general contractor the needed a/v devices did not arrive via UPS as desired. Inspection is to be rescheduled.
FIR07-00904 INSP-Alarm Testing11/20/200711/21/200711/21/2007 12:18:30 PMPCANC
Call Robert at ###-####, Phone #: ###-#### Internet Inspection Request from: Robert Gobler Inspection cancelled from web by: Robert Gobler
FIR07-00919 INSP-Final Inspection11/20/200711/21/200711/21/2007 11:29:45 AMAFAIL
Per the general contractor the needed a/v devices did not arrive via UPS as desired. Inspection is to be rescheduled.
FIR07-00919 INSP-Alarm Testing11/20/200711/21/200711/21/2007 11:29:09 AMAFAIL
Per the general contractor the needed a/v devices did not arrive via UPS as desired. Inspection is to be rescheduled.
BLD07-00772 FIRE-Final Inspection11/20/200711/21/200711/21/2007 11:27:57 AMAFAIL
The contractor wanted a partial fire life safety for the remodeled area of the main lobby. I found emergency lights not operating, sprinkler heads with plastic shipping clips still installed and one sprinkler head deflector bent.
BLD07-02974 FIRE-Final Inspection11/20/200711/21/200711/21/2007 10:05:30 AMAPASS
Life safety passed.