FIR10-00035
| FIR-Aging Inspection | 11/21/2011 | 11/21/2011 | 11/22/2011 8:12:33 AM | | PEND |
|
|
|
FIR11-00301
| INSP-Sprinkler Rough-in | 11/21/2011 | 11/21/2011 | 11/21/2011 6:47:43 PM | P | PART |
|
|
UG fire supply line and remote FDC piping at the NW corner inspected prior to cover. Contractor has installed mechanical joint restraints in place of thrust blocks.
|
FIR11-00528
| INSP-Conference | 11/21/2011 | 11/21/2011 | 11/21/2011 6:35:54 PM | P | DONE |
|
|
Conversations with general and sub contractors regarding noted correction items.
|
BLD11-02779
| FIRE-Final Inspection | 11/18/2011 | 11/21/2011 | 11/21/2011 6:33:46 PM | P | PASS |
|
|
|
FIR11-00301
| INSP-Sprinkler Rough-in/Hydro | 11/18/2011 | 11/21/2011 | 11/21/2011 6:32:49 PM | A | PART |
|
|
UG hydrostatic test for the NW fire supply line and remote FDC piping completed satisfactory.
|
FIR11-00456
| INSP-Final Inspection | 11/18/2011 | 11/21/2011 | 11/21/2011 6:31:00 PM | A | PEND |
|
|
Scope of work is complete. Final pending adjustments to coverage at two locations. Unistrut installed adjacent to pendent heads obstructs pattern development.
|