BLD16-02147
| FIRE-Final Inspection | 11/21/2017 | 11/21/2017 | 11/24/2017 10:23:56 AM | P | FAIL |
|
|
Still waiting for Opticon erification for the gates
Phone #: ###-#### Inspection requested via web by Jeff Hannes
|
NAF17-00072
| INSP-Final | 11/20/2017 | 11/21/2017 | 11/21/2017 2:34:29 PM | P | DONE |
|
|
Permit finaled. Suppression system functioned correctly
|
BLD17-01593
| FIRE-Final Inspection | 11/20/2017 | 11/21/2017 | 11/21/2017 9:45:22 AM | A | PASS |
|
|
Life safety passed
Mandee Phone #: ###-####
|
BLD17-04209
| FIRE-Final Inspection | 11/20/2017 | 11/21/2017 | 11/21/2017 9:24:58 AM | A | FAIL |
|
|
LIfe safety will be ok to final when a separate fire alarm permit is finaled for the overspaced ceiling mounted strobe in the Office/BreakRoom.
Marva Phone #: ###-####
|
FIR17-00432
| INSP-Sprinkler Rough-in | 11/20/2017 | 11/21/2017 | 11/21/2017 8:29:39 AM | A | PASS |
|
|
The exterior canopies have been fire blocked to less than 160 cubic feet. They are ok for cover.
|
FIR17-00656
| INSP-Final Inspection | 11/20/2017 | 11/21/2017 | 11/21/2017 8:03:45 AM | A | FAIL |
|
|
Project is not ready for a final. Todays inspection was just for a rough-in. Hard lids are ok to cover. The remaining piping is not ok for cover. I noted three overspaced pendant heads in the large open area.
|