ELE18-04487
| Temporary Service | 11/21/2018 | 11/21/2018 | 11/21/2018 1:14:39 PM | P | PASS |
|
|
Please call Lee 1/2 hour prior to inspection at ###-####. Thank you! Have a terrific Thanksgiving! Phone #: ###-#### Inspection requested via web by Tricia Henderson Disconnect all loads not used. t/s o/h rec ok.
|
ELE18-04473
| Electrical Rough-In | 11/20/2018 | 11/21/2018 | 11/21/2018 11:55:52 AM | A | PASS |
|
|
Jeremy Phone #: ###-#### Ok cover front soffit entry.
|
ELE18-04453
| Electrical Rough-In | 11/19/2018 | 11/21/2018 | 11/21/2018 10:31:50 AM | A | PASS |
|
|
listing inspection for solar panels and inverters. The crew will be there from 8am to noon. Thanks guys, Ryan King Phone #: ###-#### Inspection requested via web by Ryan King All components UL listed.
|
ELE13-02738
| Final | 11/21/2018 | 11/21/2018 | 11/21/2018 9:56:56 AM | A | PASS |
|
|
GFI for floor heat functions properly. Homeowner talked to manu and explained what was going on.and they said that the unit was functioning correctly. GFI trip light was very dim, but was on to show floor heat was re-setting after a manual trip.
|
ELE18-03235
| Final | 11/20/2018 | 11/21/2018 | 11/21/2018 9:53:44 AM | A | PASS |
|
|
Garage code is 5588 Thanks!!! Phone #: ###-#### Inspection requested via web by Dustin Kuester Ok final. Floor heat GFI functions properly.
|
ELE18-04437
| Final | 11/20/2018 | 11/21/2018 | 11/21/2018 8:45:44 AM | A | PASS |
|
|
Please call the customer when on the way at ###-#### and call our technician Wayne with any questions at ###-####. Phone #: ###-#### Inspection requested via web by William Salts Ok final. Intersystem installed, panel labeled.
|
ELE18-04434
| Electrical Rough-In | 11/20/2018 | 11/21/2018 | 11/20/2018 12:31:02 PM | A | PASS |
|
|
Floor Heat Inspection, Bath Remodel R/I. Please call Fred @ ###-#### or Mike Cole ###-#### Phone #: ###-#### Inspection requested via web by Bonnie Page Ok cover mstr floor heat. Looked at on 11/20 after talking with and meeting electrical contractor.
|