ELE19-04512
| Electrical Rough-In | 11/20/2019 | 11/21/2019 | 11/21/2019 2:32:37 PM | P | PASS |
|
|
Bill Peace is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Discussed 210.71, confirmed number of receptacles required for meeting room. Count number of receptacles as per 210.52(A) applys then that total number can be placed where owner or tenant needs. floor and furniture receptacles count in total number in that room. Space is located north of east ramp off 6th street. Access shall be provided for all boxes above ceiling. Walls only rough in ok cover
|
ELE19-03664
| Final | 11/21/2019 | 11/21/2019 | 11/21/2019 1:45:27 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins Dated and initialed Final card. Final ok
|
ELE19-04459
| Final | 11/20/2019 | 11/21/2019 | 11/21/2019 1:13:15 PM | P | PASS |
|
|
Area code 801. Final solar inspection. Plans are on site at the Solaredge inverter. Phone #: ###-#### Inspection requested via web by Ashley Lanham NM cable noted changed to UF. Final ok
|
ELE19-04056
| Final | 11/20/2019 | 11/21/2019 | 11/21/2019 12:06:38 PM | A | FAIL |
|
|
electrical final. Brett is the contact Phone #: ###-#### Inspection requested via web by Deb Morton Furniture not complete as per 314.25, listing verified. Must be a ceiling inspection, lighting retro being done throughout. Must verify listing and seismic wires for all new luminaires as per 110.3 and 300.11
|
ELE19-03019
| Final | 11/20/2019 | 11/21/2019 | 11/21/2019 11:31:38 AM | A | FAIL |
|
|
Will be open, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn 110.22- Furnace disconnect shell be identified as to its purpose. 210.12- All outlets located in bedroom areas shall have AGCI proteciton. 210.52(A)- Wall space 24" and wider shall have a receptacle outlet installed to serve wall space. Left of fireplace. 210.52(C)- Pantry counter space shall have receptacle outlets installed to serve counter space.
|
ELE19-04338
| Electrical Rough-In | 11/21/2019 | 11/21/2019 | 11/21/2019 10:56:06 AM | A | PASS |
|
|
please call 30 minutes ahead if possible. Kip is the contact at ###-#### Phone #: ###-#### Inspection requested via web by Kerri Hamilton Rough in of pathways encasing mc rough in ok cover
|
ELE19-04502
| Electrical Rough-In | 11/20/2019 | 11/21/2019 | 11/21/2019 10:54:32 AM | A | PASS |
|
|
Uffer groung inspection. Please call Craig Timmons 10 minutes before heading to the inspection so he can meet you there. Craig has a couple of questions he needs clarification on. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Concrete encased on S.E. corner rouhg in ok cover.
|
ELE19-04502
| Conference | 11/21/2019 | 11/21/2019 | 11/21/2019 10:54:19 AM | P | PASS |
|
|
Uffer groung inspection. Please call Craig Timmons 10 minutes before heading to the inspection so he can meet you there. Craig has a couple of questions he needs clarification on. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek 230.6- Discussed service entrance conductors pathway to level 3. As per print 2nd service located on level 3. Service entrance conductors shall either be concidered outside building or be encased in concrete or brick to be concidered outside building. Discussed common grounding electrode discribed in 250.58.
|