BLD14-03688
| BLD-Final | 11/21/2016 | 11/22/2016 | 11/22/2016 3:28:19 PM | P | PART |
|
|
Requesting TCO on levels 1-4 of Annex Phone #: ###-#### Inspection requested via web by Joe Borelli ok for temp occ
|
BLD16-03923
| BLD-Foundation | 11/22/2016 | 11/22/2016 | 11/22/2016 3:27:52 PM | P | PASS |
|
|
Hans Phone #: ###-####
|
BLD15-02658
| BLD-Final | 11/22/2016 | 11/22/2016 | 11/22/2016 3:27:41 PM | P | CANC |
|
|
bob Phone #: ###-####
|
BLD16-00147
| BLD-Conference | 11/22/2016 | 11/22/2016 | 11/22/2016 1:38:41 PM | P | PASS |
|
|
Shafts on 5th Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD15-03403
| BLD-Conference | 11/22/2016 | 11/22/2016 | 11/22/2016 1:38:30 PM | P | PASS |
|
|
Josua-please call 30 minutes prior to meet Phone #: ###-####
|
BLD16-02958
| BLD-Other | 11/22/2016 | 11/22/2016 | 11/22/2016 1:38:13 PM | P | PEND |
|
|
Bob-ceiling inspection to cover Phone #: ###-#### ok to flood after elec oks
|
BLD16-03368
| BLD-Framing/Rough-in | 11/21/2016 | 11/22/2016 | 11/22/2016 12:59:55 PM | A | PASS |
|
|
Larren Phone #: ###-####
|
BLD16-02857
| BLD-Final | 11/22/2016 | 11/22/2016 | 11/22/2016 12:21:51 PM | P | PASS |
|
|
this is the early start permit-i didn't schedule the final once the actual building permit was issued-can you check this one and finial it for me? I don't believe there were any inspections done before the actual buildinbg permit was issued-thanks CAN
|
BLD16-02630
| BLD-Framing/Rough-in | 11/21/2016 | 11/22/2016 | 11/22/2016 12:15:38 PM | A | PART |
|
|
bob Phone #: ###-#### ok to cover north side insulation and framing ok
|
BLD16-04246
| BLD-Final | 11/21/2016 | 11/22/2016 | 11/22/2016 11:06:20 AM | P | PART |
|
|
Caleb Phone #: ###-#### ok for temp occ needs ada 36 '' countertop
|
BLD16-03672
| BLD-Framing/Rough-in | 11/21/2016 | 11/22/2016 | 11/22/2016 10:54:24 AM | A | PASS |
|
|
ron Phone #: ###-####
|
BLD15-02707
| BLD-Framing/Rough-in | 11/21/2016 | 11/22/2016 | 11/22/2016 10:54:09 AM | A | PEND |
|
|
Beginning exterior sheathing. We like to review framing and screwing requirements. Phone #: ###-#### Inspection requested via web by Jim Williams need to see details
|
BLD15-04184
| BLD-Framing/Rough-in | 11/21/2016 | 11/22/2016 | 11/22/2016 9:57:59 AM | A | PASS |
|
|
Framing Inspection Phone #: ###-#### Inspection requested via web by Ami Tracy first second floors ok to one side int walls and cover ext walls 4orth floor ok to cover walls
|
BLD15-04078
| BLD - Request for Extension | 11/21/2016 | 11/22/2016 | 11/22/2016 9:53:11 AM | A | DONE |
|
|
Nate Phone #: ###-####
|
BLD16-03780
| BLD-Final | 11/21/2016 | 11/22/2016 | 11/22/2016 9:08:43 AM | A | NR |
|
|
Call Alex McKinley 30 minutes prior to meet on site. Phone #: ###-#### Inspection requested via web by Alex McKinley needs an elc final
|