Inspections for the day of: Monday, November 26, 2007.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00033 INSP-Conference11/26/200711/26/200711/26/2007 4:09:21 PMPDONE
Job scheduling.
FIR07-00333 INSP-Alarm Testing11/26/200711/26/200711/26/2007 3:54:18 PMPDEFR
Inspection request intended for the shell and core alarm work, items tested today include fire sprinkler monitoring of the fire pump, controller, power supplies, dry system, tampers, flows, etc. Outside bell does not function at pump flow switch, need 12 ah batteries at the FACP, tamper at the standpipe control valve is not correct.
FIR06-00504 INSP-Final Inspection11/21/200711/26/200711/26/2007 3:46:04 PMAPART
Completed sprinkler monitoring testing including the dry system, fire pump, controller and power supplies, noted a QOD is not required on the dry system, missing coverage at the stairs to the basement electrical room, need signage at valves, missing head boxes, finish pack, need to complete forward flow of the BFP, also need to complete a final shell system walkthrough.
FIR07-00939 INSP-Final Inspection11/26/200711/26/200711/26/2007 3:39:52 PMPPASS
Fire sprinkler permit finaled.
BLD07-02607 FIRE-Final Inspection11/26/200711/26/200711/26/2007 1:17:27 PMPFAIL
Provide signage at the main entry/exit door, repair one exit sign and one EM light at the office area entrance, provide one 2A10BC PFE for the 1st floor offices, remove existing fire extinguisher signage at four locations in the warehouse area where no longer applicable, missing one exit discharge light at the west side.
FIR07-00469 FIR-Aging Inspection11/26/200711/26/200711/26/2007 11:57:40 AM DEFR
Work in progress