Inspections for the day of: Wednesday, November 26, 2014.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-00332 General Inspection11/26/201411/26/201412/1/2014 3:51:05 PM PASS
Initial site prep work is starting to begin at TV Steel. Permit is posted on gate, perimeter wattles are installed, and no trackout to Supply Way. Approved.
ESC14-00404 General Inspection11/26/201411/26/201412/1/2014 3:38:44 PM PASS
WIP on warehouse packaging center expansion. BMPs are installed and include perimeter wattles, concrete washout, and permit signage. No trackout or sediment discharges offsite. No corrections needed at this time.
ESC13-01309 Aging Inspection11/26/201411/26/201412/1/2014 8:52:38 AM CANC
ESC13-01308 Aging Inspection11/26/201411/26/201412/1/2014 8:52:25 AM CANC
ESC13-01307 Aging Inspection11/26/201411/26/201412/1/2014 8:52:12 AM CANC
ESC13-01306 Aging Inspection11/26/201411/26/201412/1/2014 8:51:59 AM CANC
ESC14-00408 General Inspection11/26/201411/26/201412/1/2014 8:40:03 AM PASS
ESC14-01003 Site Preparation11/26/201411/26/201411/26/2014 10:37:18 AMPPASS
Clint Phone #: ###-####

Permit posted. Tahoe Homes in progress at East Valley are in compliance. Drop inlets have filter protection. Lined concrete washout is installed and being utilized. Approved for excavation.
ESC14-00360 General Inspection11/26/201411/26/201411/26/2014 10:28:49 AM PASS
WIP. Frame is up. Site has good structural and vegetative perimeter containment. Minimal trackout from foot traffic. Permit posted. No corrections at this time.
ESC14-00381 General Inspection11/26/201411/26/201411/26/2014 10:13:35 AM PASS
No current activity at BH #5 stockpile. An earthen berm has been installed 50 meters up from end of Windsong and divert sheet flow the stormwater drainage pond. The old rock construction entrance is still installed but will need to be replenished when activity increases.

Next week, the SFH on Birdsong Ct. will be using some of the dirt to backfill his site. I alerted him that he will be required to clean up any trackout and restore BMPs
ESC14-00106 General Inspection11/25/201411/26/201411/26/2014 10:08:31 AMPPASS
Minor construction and finishing touches are complete. Site is landscaped and with sod and rock. Perimeter has been hydroseeded and a bond issued for hillside revegetation. Will monitor stabilization. No issues or erosion rills occuring.
ESC14-01035 Site Preparation11/25/201411/26/201411/26/2014 9:46:36 AMAPASS
MICHEAL Phone #: ###-####

Meeting conducted onsite with RP/GC. Site is situated in a topographical depression and receives some drainage from offsite. On the back there is an existing vegetated drainage channel. A fiber wattle has been trenched in to trap sediment.

Inlet protection needs to be replaced on corner of Birdsong and Windsong. Micheal will coordinate with JH to get those installed this week.

Permit posted. ESC plan onsite.

Excavation scheduled for Friday or Monday. Once initial fill is conducted a stabilized entrance will be provided.

Approved.
ESC14-00296 Tracking Control11/25/201411/26/201411/26/2014 9:22:44 AMAPART
Sweeper service was at site at 4 PM yesterday and cleaned up much of the trackout caused by yesterday's activity. Site is digging deeping and offhauling dirt, so there is heavy vehicle traffic.

Current BMPs to reduce trackout and effects on MS4 system are:

1.Sweeping wheels and knocking mud off trucks at the exit point.
2. Manual sweeping of the intersection on Capitol and Main.
3. DI protection (need to verify fiber mats have been installed).
4. Sweeper service should come 2x again today