Inspections for the day of: Wednesday, November 27, 2019.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-04340 BLD-Framing/Rough-in11/26/201911/27/201911/27/2019 4:30:04 PMPPART
Tom Phone #: ###-####//walls only//talked with Tom about fire sprinklers-advised to discuss with Troy//
BLD19-01789 BLD-Final11/26/201911/27/201911/27/2019 4:29:04 PMPNR
Vanessa Phone #: ###-####//need mechanical final and smoke , smoke carbon monoxide detectors in locations discussed//
BLD19-02871 BLD-Final11/27/201911/27/201911/27/2019 3:06:06 PMPCANC
Office number Phone #: ###-####//not ready//CN still poste//
BLD19-02650 BLD-Final11/26/201911/27/201911/27/2019 2:27:06 PMPPASS
Maureen Phone #: ###-####//no changes to existing//final complete//
BLD18-04229 BLD-Final11/27/201911/27/201911/27/2019 1:39:08 PMPNR
Robert Phone #: ###-####//exterior not complete//discussed with owner, he will call Jim who he has been working with on project//
BLD19-03934 BLD-Final11/27/201911/27/201911/27/2019 12:31:28 PMPFAIL
Brandy Phone #: ###-####//CN posted//need to add anchors on south end per engineering//
BLD19-02063 BLD-Final11/27/201911/27/201911/27/2019 11:38:06 AMPFAIL
Call for access to get inside the building- Chris Phone #: ###-####//foundation vents covered with plastic--needs to be open to underfloor//add insulation to crawl space hatch//provide blower door test and post results//
BLD19-03841 BLD-Conference11/27/201911/27/201911/27/2019 11:04:09 AMAPASS
Portal frame has been reinstalled and the Engineer has done a site inspection a has a new stamped areas of correction for the framing Phone #: ###-#### Inspection requested via web by Brad Pfannmuller//shear ok per plans//clarification for hold downs provided and stamped by design engineer//nailing ok//hold downs installed correctly//finish sheating at bottom of walls with same nailing patterns//
BLD19-03076 BLD-Final11/26/201911/27/201911/27/2019 10:32:44 AMAPASS
Natalie Phone #: ###-####//existing flashing used//no change in size//
BLD19-03076 DOC - Permit Finaled11/27/201911/27/201911/27/2019 10:32:09 AMPPASS
BLD19-03657 BLD-Wall Bracing11/25/201911/27/201911/27/2019 10:17:00 AMAFAIL
Mark Phone #: ###-####/need to add blocking on first story at all panel edges at shear locations(some vertical blocking will be needed)//Let GC know about eaves that will need to be 24 inches from PL//re-inspection required//
BLD19-03841 BLD-Conference11/27/201911/27/201911/27/2019 10:15:53 AMACANC
Portal frame has been reinstalled and the Engineer has done a site inspection a has a new stamped areas of correction for the framing Phone #: ###-#### >> Inspection requested via web by Brad Pfannmuller Inspection cancelled from web by: Brad Pfannmuller
BLD16-02407 BLD-Final11/26/201911/27/201911/27/2019 9:37:28 AMAPASS
Joe Phone #: ###-####//added fire separation per Jim Sly at attic separation--ok//plans show exisitng door to remain-had them add self closing hinges//final complete per plans//
BLD16-02407 DOC - Permit Finaled11/27/201911/27/201911/27/2019 9:37:03 AMPPASS
BLD19-02713 BLD-Final11/20/201911/27/201911/27/2019 9:16:33 AMACANC
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher//talked with contact, said footings were done with remodel,,will reschedule for Jim//
BLD19-03598 BLD-Energy code compliance11/26/201911/27/201911/27/2019 9:04:52 AMAPASS
Inspection in mudroom addition. Insulation R-20 spray in. Also please check framing in carport beam. OK to cover? Could we please get inspection before 9am? if not could inspector please call ###-#### Tara Thank you! Phone #: ###-#### Inspection requested via web by Tara Vreeland
BLD18-03079 BLD-Aging Inspection11/27/201911/27/201911/27/2019 8:49:41 AM DONE
Expires: 01/12/20