BLD1056006
| INSP - Framing/Rough-in | 11/28/1995 | 11/28/1995 | 11/28/1995 12:00:00 AM | | CANC |
|
|
11/26/95 342 -
|
BLD95-00592
| INSP - Masonry | 11/28/1995 | 11/28/1995 | 11/28/1995 12:00:00 AM | | PART |
|
|
11/26/95 342 - GROUT BOND BEAM George on site for a conference. Special inspectors are supposed to be o
|
BLD95-02025
| INSP - Foundation | 11/28/1995 | 11/28/1995 | 11/28/1995 12:00:00 AM | | PASS |
|
|
/ / 342 - setbacks ok
|
BLD95-00592
| INSP - Masonry | 11/27/1995 | 11/28/1995 | 11/28/1995 12:00:00 AM | A | NR |
|
|
11/28/95 342 - GROUT BOND BEAM no one there for masonry or supervision ì
|
BLD95-01293
| INSP - Framing/Rough-in | 11/28/1995 | 11/28/1995 | 11/28/1995 12:00:00 AM | P | PART |
|
|
11/28/95 342 - 1:15 APPOINTMENT. OK to cover ceiling and interior walls
|
BLD95-01733
| INSP - Foundation | 11/28/1995 | 11/28/1995 | 11/28/1995 12:00:00 AM | P | PART |
|
|
11/28/95 342 - early pm. poured, but had looked at rebar previously, need to ck wall width and co to South as to structural capacity. Architect is cutting corners ???
|
BLD95-02025
| INSP - Footings | 11/28/1995 | 11/28/1995 | 11/28/1995 12:00:00 AM | P | PASS |
|
|
11/28/95 342 - cleaning out mud and loose soil, and will use a "pour in
|