MEC05-03868
| Final | 11/25/2005 | 11/28/2005 | 11/28/2005 3:35:50 PM | P | PASS |
|
|
Please inspect as late as possible. Call with any problems. Thanks, April.; Phone #: ###-#### Internet Inspection Request from: APRIL THOMAS
|
MEC05-03551
| Rough-in | 11/25/2005 | 11/28/2005 | 11/28/2005 3:10:50 PM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 11/25/2005 at 10:36:59 AM. Contact: ###-####.
|
MEC05-03721
| Rough-in | 11/28/2005 | 11/28/2005 | 11/28/2005 1:52:51 PM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 11/28/2005 at 10:55:16 AM. Contact: ###-####. need to install smoke detector upstream of outside air on one of the three heat pumps only, heat pump nearest to front entry of t/i lobby
|
MEC05-03859
| Rough-in | 11/23/2005 | 11/28/2005 | 11/28/2005 1:35:32 PM | P | PASS |
|
|
Please contact job foreman, Don Clover - ###-####. Internet Inspection Request from: RaChelle Meister
|
MEC05-03849
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:02:27 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03848
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:02:17 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03847
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:02:07 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03846
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:01:54 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03845
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:01:43 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03844
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:01:33 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03843
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:01:20 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03842
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:01:03 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03841
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:00:52 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03840
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:00:41 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03839
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:00:29 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03838
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:00:18 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03837
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 1:00:06 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03836
| Conference | 11/23/2005 | 11/28/2005 | 11/28/2005 12:59:50 PM | A | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-02784
| MEC-Aging Inspection | 11/28/2005 | 11/28/2005 | 11/28/2005 12:58:30 PM | | CANC |
|
|
wip
|
MEC05-02333
| MEC-Aging Inspection | 11/28/2005 | 11/28/2005 | 11/28/2005 12:57:28 PM | | PASS |
|
|
|
MEC05-03850
| Final | 11/23/2005 | 11/28/2005 | 11/28/2005 12:46:41 PM | A | NH |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03513
| Pressure Test | 11/25/2005 | 11/28/2005 | 11/28/2005 12:46:13 PM | A | FAIL |
|
|
Phone #: ###-#### Internet Inspection Request from: APRIL THOMAS
|
MEC05-03755
| Rough-in | 11/27/2005 | 11/28/2005 | 11/28/2005 12:45:38 PM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/27/2005 at 10:52:48 PM. Contact: ###-####.pressure test ok too
|
MEC05-03870
| Pressure Test | 11/25/2005 | 11/28/2005 | 11/28/2005 9:11:19 AM | A | PASS |
|
|
###-####
|
MEC05-02333
| DOC - Permit Finaled | 11/28/2005 | 11/28/2005 | 11/28/2005 12:00:00 AM | P | PASS |
|
|
|
MEC05-03836
| DOC - Permit Finaled | 11/28/2005 | 11/28/2005 | 11/28/2005 12:00:00 AM | P | PASS |
|
|
Tool hook up project in clean room.; Phone #: ###-#### Internet Inspection Request from: xenon long
|
MEC05-03868
| Conference | 11/25/2005 | 11/28/2005 | 11/25/2005 3:12:36 PM | P | CANC |
|
|
Please inspect as late as possible. Call with any problems. Thanks, April.; Phone #: ###-#### Internet Inspection Request from: APRIL THOMAS Inspection cancelled from web by: APRIL THOMAS
|