Inspections for the day of: Tuesday, November 28, 2006.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-02282 FIRE-Final Inspection11/28/200611/28/200611/28/2006 4:46:42 PMPFAIL
Provide tag for the fire extinguisher and the correct sticker as discussed for the main exit door.
FIR06-00824 INSP-Sprinkler Rough-in/Hydro11/28/200611/28/200611/28/2006 4:45:37 PMPPASS
The 24 hour air test began at 12:30 with the guage reading 43 psi
FIR06-00740 INSP-Final Inspection11/28/200611/28/200611/28/2006 3:15:43 PMPPASS
permit finaled
FIR06-00543 INSP-Sprinkler Rough-in/Hydro11/27/200611/28/200611/28/2006 3:10:02 PMPFAIL
Before I give the ok to cover the sprinkler piping associated with this scope of work the shell/core piping needs to be inspected and passed. These inspections have not been called in and the plans were not on the job site.
FIR06-00914 INSP-Final Inspection11/27/200611/28/200611/28/2006 3:00:44 PMAPASS
Permit finaled. Todd is contacting the property manager about providing the knox box
BLD06-00658 FIRE-Final Inspection11/28/200611/28/200611/28/2006 1:46:28 PMPPASS
life safety finaled
FIR05-00536 INSP-Sprinkler Rough-in11/28/200611/28/200611/28/2006 12:58:57 PMPPASS
See city approved plans for locations on 4th floor where piping is ok to cover in the hardlid areas.
FIR05-00827 INSP-Sprinkler Rough-in11/28/200611/28/200611/28/2006 12:58:19 PMPPASS
Sprinkler piping ok to cover
BLD06-02084 FIRE-Final Inspection11/27/200611/28/200611/28/2006 12:45:24 PMAFAIL
No approved plans on site for inspection
FIR06-00847 INSP-Final Inspection11/27/200611/28/200611/28/2006 9:50:18 AMAPASS
permit finaled