FIR09-00530
| FIR-Aging Inspection | 11/29/2010 | 11/29/2010 | 11/30/2010 10:04:45 AM | | NR |
|
|
work is in progress
|
FIR04-00376
| INSP-Conference | 11/19/2010 | 11/29/2010 | 11/30/2010 9:42:00 AM | A | DONE |
|
|
Alex with Oxarc is following up on inspection.
|
FIR04-00375
| INSP-Conference | 11/19/2010 | 11/29/2010 | 11/30/2010 9:41:01 AM | A | DONE |
|
|
Alex with Oxarc is following up on inspection.
|
FIR04-00374
| INSP-Conference | 11/19/2010 | 11/29/2010 | 11/30/2010 9:39:39 AM | A | DONE |
|
|
Alex with Oxarc is following up on inspection.
|
BLD10-02736
| FIRE-Final Inspection | 11/29/2010 | 11/29/2010 | 11/29/2010 3:33:48 PM | P | CANC |
|
|
I spoke to Bob and he stated that there was no paper work at the project site. I contacted Jim Sly and he was going to contact Bob and go over the requirements for an inspection.
|
BLD10-02723
| FIRE-Final Inspection | 11/29/2010 | 11/29/2010 | 11/29/2010 3:31:17 PM | P | FAIL |
|
|
Need to provide atleast three fire extinguishers as discussed and the AES system needs to be inspected and finaled prior to occupancy.
|
BLD10-02086
| FIRE-Final Inspection | 11/29/2010 | 11/29/2010 | 11/29/2010 3:30:05 PM | P | FAIL |
|
|
Sid and I found that the door mags are not connected to the fire alarm panel. Also Sid needs to get approval to use the alarm/intercom system for the common use restroom corridor.
|
FIR10-00558
| INSP-Final Inspection | 11/29/2010 | 11/29/2010 | 11/29/2010 2:54:12 PM | P | FAIL |
|
|
The canopies are installed but the ceiling tile is still missing.
|
FIR10-00596
| INSP-Final Inspection | 11/29/2010 | 11/29/2010 | 11/29/2010 11:31:59 AM | P | PASS |
|
|
Permit finaled.
|
FIR10-00032
| INSP-Sprinkler Rough-in | 11/29/2010 | 11/29/2010 | 11/29/2010 11:30:39 AM | P | PASS |
|
|
See the city approved plans for the office where the sprinkler piping can be covered.
|