BLD12-02380
| FIRE-Conference | 11/29/2013 | 11/29/2013 | 11/29/2013 4:41:23 PM | P | DONE |
|
|
Regarding items to be finished prior to final.
|
FIR13-00576
| INSP-Sprinkler Rough-in | 11/29/2013 | 11/29/2013 | 11/29/2013 4:39:43 PM | P | PART |
|
|
C/N items finished. Remainder of overhead rough-in passed inspection including added heads at entry vestibule, branch line restraints, seismic bracing.
|
FIR12-00723
| INSP-Final Inspection | 11/27/2013 | 11/29/2013 | 11/29/2013 4:37:40 PM | A | DEFR |
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus *inspection intended for 12/2
|
FIR13-00576
| INSP-Sprinkler Rough-in/Hydro | 11/27/2013 | 11/29/2013 | 11/29/2013 11:17:07 AM | A | PART |
|
|
Overhead hydrostatic testing completed satisfactory.
|
BLD13-03258
| FIRE-Final Inspection | 11/27/2013 | 11/29/2013 | 11/29/2013 11:14:41 AM | A | PASS |
|
|
Noted correction items verified for completion. Life safety passed.
|
FIR12-00605
| INSP-Final Inspection | 11/27/2013 | 11/29/2013 | 11/27/2013 3:43:22 PM | A | CANC |
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|