PLM17-03711
| Water and/or Sewer | 11/28/2017 | 11/29/2017 | 11/29/2017 3:04:58 PM | P | PART |
|
|
Water only inspection. Mike Jackson ###-#### is the PM for the Starbucks project. If you could call prior to arriving it would be appreciated. Phone #: ###-#### Inspection requested via web by judy patton. OK to cover with sand, on site, except for two joints.
|
PLM17-03052
| Final | 11/29/2017 | 11/29/2017 | 11/29/2017 2:44:24 PM | P | NH |
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen. no access
|
PLM17-03954
| Plumbing Rough-in | 11/28/2017 | 11/29/2017 | 11/29/2017 2:44:24 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
|
PLM17-01118
| Other | 11/29/2017 | 11/29/2017 | 11/29/2017 2:20:49 PM | P | NR |
|
|
|
PLM17-03950
| Final | 11/29/2017 | 11/29/2017 | 11/29/2017 2:07:04 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by bob pond
|
PLM17-04584
| Water and/or Sewer | 11/29/2017 | 11/29/2017 | 11/29/2017 1:57:55 PM | P | PASS |
|
|
Phil Phone #: ###-####. OK to cover up to the meter connection.
|
PLM17-04530
| Water and/or Sewer | 11/29/2017 | 11/29/2017 | 11/29/2017 1:57:13 PM | P | PASS |
|
|
water service stubout
|
PLM17-04608
| Final | 11/28/2017 | 11/29/2017 | 11/29/2017 1:48:09 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette
|
PLM17-04723
| Water Heater Final | 11/28/2017 | 11/29/2017 | 11/29/2017 12:06:39 PM | A | PASS |
|
|
PLEASE CALL WHEN YOU ARE ON YOUR WAY. THANK YOU! Phone #: ###-#### Inspection requested via web by JEREMY LINK
|
PLM17-01118
| Plumbing Rough-in | 11/28/2017 | 11/29/2017 | 11/29/2017 11:43:56 AM | A | NR |
|
|
|
PLM17-01671
| PLM-Aging Inspection | 11/29/2017 | 11/29/2017 | 11/29/2017 11:37:12 AM | | PEND |
|
|
Tagged the door
|
PLM17-01669
| PLM-Aging Inspection | 11/29/2017 | 11/29/2017 | 11/29/2017 11:17:14 AM | | PEND |
|
|
tagged the door
|
PLM17-04688
| Plumbing Rough-in | 11/28/2017 | 11/29/2017 | 11/29/2017 10:32:21 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Branden Steers Inspection cancelled from web by: Branden Steers
|
PLM17-04443
| Groundwork | 11/29/2017 | 11/29/2017 | 11/29/2017 10:21:26 AM | P | PASS |
|
|
Dave Phone #: ###-####
|
PLM17-04726
| Plumbing Rough-in | 11/28/2017 | 11/29/2017 | 11/29/2017 9:50:32 AM | A | PASS |
|
|
Lockbox code if no one is present. Lockbox on front door. Plumbing is up stairs on tri level replace bathtub and shower
4888 lockbox code Phone #: ###-#### Inspection requested via web by chris thornburg
|
PLM17-04530
| Water and/or Sewer | 11/28/2017 | 11/29/2017 | 11/29/2017 9:05:55 AM | A | NR |
|
|
Just a 5ft stub out from building. Should be ready mid morning at the latest. Phone #: ###-#### Inspection requested via web by Ben Taylor
|
PLM17-04329
| Water and/or Sewer | 11/28/2017 | 11/29/2017 | 11/29/2017 9:02:59 AM | A | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Mike Sanders
|
PLM17-04333
| Water and/or Sewer | 11/28/2017 | 11/29/2017 | 11/29/2017 9:01:38 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Mike Sanders. The sewer must be water or air tested. The piping is ok. Don't cover until the test is approved. Reschedule when the test is on.
|
PLM17-04727
| Water and/or Sewer | 11/28/2017 | 11/29/2017 | 11/29/2017 8:39:02 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brett Simmons
|
PLM17-04727
| DOC - Permit Finaled | 11/29/2017 | 11/29/2017 | 11/29/2017 8:38:51 AM | P | PASS |
|
|
|
PLM17-04608
| Final | 11/22/2017 | 11/29/2017 | 11/28/2017 3:15:13 PM | P | NH |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette
|