FIR05-00459
| INSP-Alarm Testing | 11/2/2005 | 11/3/2005 | 11/4/2005 10:02:08 AM | P | FAIL |
|
|
Tested theatres, need to retest two EOL , add speaker in theatre 3, still need to test and verify correct locations for duct detectors, see correction notice for listing of remaining items, final inspection not approved at this time.
|
BLD05-01669
| FIRE-Conference | 11/3/2005 | 11/3/2005 | 11/3/2005 4:37:26 PM | P | DONE |
|
|
On site discussion with Ben regarding insulation issues as they affect fire sprinklers in the attic and dormer areas.
|
FIR05-00326
| INSP-Supply line flush | 11/2/2005 | 11/3/2005 | 11/3/2005 4:35:22 PM | P | FAIL |
|
|
Provide resubmittals as required indicating information as requested on plan review notes and all field changes from original plans, overhead inspection failed due to numerous issues including spacing, head temps., bracing, seismic clearance, obstructions to discharge, riser not complete, etc., the UG was flush was performed and is acceptable.
|
FIR05-00174
| INSP-Final Inspection | 11/3/2005 | 11/3/2005 | 11/3/2005 2:02:06 PM | P | CANC |
|
|
Wrong permit number called in, this inspection was for overhead cover on permit FIR05-00405 bld #13.
|
MIS05-00194
| FIR-Final | 11/3/2005 | 11/3/2005 | 11/3/2005 1:26:43 PM | P | PASS |
|
|
Life safety passed inspection.
|
FIR05-00385
| INSP-Sprinkler Rough-in | 11/3/2005 | 11/3/2005 | 11/3/2005 12:54:03 PM | P | PART |
|
|
The 3rd floor center common area hard lid area is acceptable for cover, also discussed coverage requirements for small room at perimeter and 2nd floor hard lid areas.
|
BLD05-00672
| FIRE-Final Inspection | 11/2/2005 | 11/3/2005 | 11/3/2005 11:04:19 AM | A | NR |
|
|
Fire sprinkler permit must be finaled prior to life safety sign-off.
|
BLD04-01324
| FIRE-Final Inspection | 11/2/2005 | 11/3/2005 | 11/3/2005 10:13:40 AM | A | FAIL |
|
|
Emergency lighting and exit signs in several locations are not functional, exit doors at north and west sides are not installed yet, some exit discharge lighting is not installed on the east and south sides, fire lane marking remains to be completed, not all items reviewed at this inspection.
|
FIR05-00405
| INSP-Sprinkler Rough-in | 11/3/2005 | 11/3/2005 | 11/3/2005 12:00:00 AM | P | PART |
|
|
Insulation tenting at 3rd floor is acceptable, okay to cover, "blown in" insulation to be done after lid is sheetrocked.
|