PLM07-03775
| Final | 11/30/2007 | 11/30/2007 | 11/30/2007 4:00:45 PM | P | PART |
|
|
oked temp on final for beauty salon in building still need to meet with Bill T. with united water and owner of building on premise protection and other addition back flow devices if needed in building
|
PLM07-03918
| Plumbing Rough-in | 11/29/2007 | 11/30/2007 | 11/30/2007 3:20:03 PM | P | PASS |
|
|
Elisa Phone #: ###-####
|
PLM07-03889
| Water Heater Final | 11/26/2007 | 11/30/2007 | 11/30/2007 3:18:38 PM | P | PASS |
|
|
Please give Mrs Forsman a lead call. If no answer at above #, please call ###-####. Thank you. Phone #: ###-#### Internet Inspection Request from: Mike Dunson
|
PLM07-03854
| Final | 11/29/2007 | 11/30/2007 | 11/30/2007 1:42:22 PM | A | PART |
|
|
Phone #: ###-#### Internet Inspection Request from: Dina Reynolds re schedule inspection for 12 / 3/ 07 to meet plumber on site
|
PLM07-03571
| Final | 11/30/2007 | 11/30/2007 | 11/30/2007 11:07:08 AM | P | CANC |
|
|
PLEASE SCHEDULE FOR A LATE AFTERNOON INSPECTION. JOB CONTACT IS DOUG FRIEDMAN. Phone #: ###-#### Internet Inspection Request from: ADAM WARR Inspection cancelled from web by: JENN STALEY
|
PLM07-03922
| Water and/or Sewer | 11/29/2007 | 11/30/2007 | 11/30/2007 10:59:49 AM | A | PART |
|
|
sewer line and oil and water separator are ready now. Has test on. If we could have first thing, then we can cover and drain out. thanks Phone #: ###-#### Internet Inspection Request from: Bonnie Gilbert interceptor and down stream piping test ok need to repipe first chamber vent to tank and cap off vent on inlet side of interceptor ok to cover down stream piping
|
PLM07-03662
| Groundwork | 11/29/2007 | 11/30/2007 | 11/30/2007 10:31:22 AM | A | PASS |
|
|
billy Phone #: ###-####
|
PLM07-03921
| Plumbing Rough-in | 11/29/2007 | 11/30/2007 | 11/30/2007 9:56:06 AM | A | PASS |
|
|
lori - pera plm Phone #: ###-#### rough-in for master bath only ok on this phase of construction
|