BLD09-01819
| FIRE-Final Inspection | 11/20/2009 | 11/30/2009 | 12/1/2009 12:30:22 PM | A | FAIL |
|
|
This was a follow up for a final inspection with Bill Matter. The life safety can not be finaled yet due to problems with the project related fire sprinkler permit and of the two doors requiring corrected door hardware only one door was addressed.
|
FIR09-00449
| INSP-Conference | 11/30/2009 | 11/30/2009 | 11/30/2009 3:11:10 PM | P | CANC |
|
|
Per phone conversation with Rob, this inspection will be rescheduled for tomorrow morning.
|
FIR09-00408
| INSP-Supply line flush | 11/30/2009 | 11/30/2009 | 11/30/2009 3:06:27 PM | P | PASS |
|
|
The underground flush passed.
|
BLD09-02079
| FIRE-Final Inspection | 11/30/2009 | 11/30/2009 | 11/30/2009 3:00:44 PM | P | PASS |
|
|
Life safety passed. I had the property manager remove two thumbturn deadbolts from the interior doors while I waited. Also per Carl Madsen the plans do not need to be resubmitted due to the floor plan not matching exactly.
|
FIR09-00672
| INSP-Alarm Testing | 11/30/2009 | 11/30/2009 | 11/30/2009 2:58:38 PM | P | PASS |
|
|
Permit finaled. EOL voltage verified for atleast 19.6 minimum.
|
FIR09-00468
| INSP-Final Inspection | 11/27/2009 | 11/30/2009 | 11/30/2009 2:04:30 PM | A | FAIL |
|
|
The operation of the hvac system when activated from the jail side failed. Six of the sprinkler system tamper switches failed to function correctly. Need to verify that the doors on the main level have been adjusted for closure since they previously failed. Addtional smoke detectors, pull stations smoke detectors, dampers and duct detectors tested ok today.
|
FIR09-00030
| INSP-Final Inspection | 11/30/2009 | 11/30/2009 | 11/30/2009 2:02:00 PM | P | PASS |
|
|
Permit finaled
|
BLD08-01370
| FIRE-Final Inspection | 11/30/2009 | 11/30/2009 | 11/30/2009 2:01:20 PM | P | PASS |
|
|
Life safety passed.
|
FIR09-00520
| INSP-Final Inspection | 11/25/2009 | 11/30/2009 | 11/30/2009 11:45:28 AM | A | PASS |
|
|
Permit finaled
|