Inspections for the day of: Monday, November 4, 2013.
Number of inspections: 14
Percentage of inspections complete: 86 %
Percentage of inspections not complete: 14 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-01539 BLD-Other10/31/201311/1/2013 P 
rebar on a slab // charles Phone #: ###-####
BLD13-01688 BLD-Framing/Rough-in11/1/201311/1/2013 P 
Charles Phone #: ###-####
BLD13-02674 BLD-Framing/Rough-in11/4/201311/4/201311/4/2013 4:28:09 PMPNR
Wes Phone #: ###-####. Needs other trades rough in minspections first.
BLD13-01289 BLD-Wall cover11/4/201311/4/201311/4/2013 3:39:40 PMPPART
Screw inspection Phone #: ###-#### >> Inspection requested via web by Mike McHargue. 3rd floor, North and south end units, interior shear walls, party walls and corridor walls ok. All firestopping completed. Ok to tape and cover.
BLD13-02159 BLD-Framing/Rough-in11/4/201311/4/201311/4/2013 2:01:38 PMPFAIL
Please call Mike Oborn prior to arrival. He is the contractor for all the framing. Thanks Phone #: ###-#### >> Inspection requested via web by Matt Perry. No approved plans on site. Called Mike twice prior to arrival, no answer and could not leave message, voice mailbox full. Will need to reschedule.
ESC13-00880 General Inspection11/4/201311/4/201311/4/2013 1:45:58 PMPPASS
BLD13-02392 BLD-Other11/4/201311/4/201311/4/2013 1:45:36 PMPPASS
clarence Phone #: ###-####. OK to insulate.
ESC13-00269 General Inspection11/4/201311/4/201311/4/2013 1:26:59 PMPPASS
BLD13-00645 BLD-Energy code compliance11/1/201311/4/201311/4/2013 1:26:30 PMPPASS
Requesting Energy Code Inspection for exterior insulation systems on the South Half of the building. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD13-00552 BLD-Wall cover11/1/201311/4/201311/4/2013 11:47:47 AMANR
Fastening on firewall assembly...interior sheetrock Phone #: ###-#### >> Inspection requested via web by Brian Stark
BLD13-00550 BLD-Wall cover11/1/201311/4/201311/4/2013 11:26:36 AMANR
Interior firewall fastening Phone #: ###-#### >> Inspection requested via web by Brian Stark
ESC13-00597 Random Inspection11/4/201311/4/201311/4/2013 10:27:39 AMAPASS
BLD13-02234 BLD-Final11/1/201311/4/201311/4/2013 10:27:08 AMANR
luke Phone #: ###-#### - call prior . Needs pther trades finals.
BLD13-01688 BLD-Framing/Rough-in11/1/201311/4/201311/4/2013 10:26:41 AMAPASS
Interior steel stud walls at phase 1, part B. Gridlines 4 to 5.7 and grid lines C to E (Admin offices) ok to cover.