BLD01-02850
| FIRE-Final Inspection | 11/2/2001 | 11/5/2001 | 11/5/2001 12:00:00 AM | A | PASS |
|
|
###-####
|
BLD00-02920
| FIRE-Conference | 11/5/2001 | 11/5/2001 | 11/5/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 409 On 11/5/2001 10:39:52 AM checked operation of blast doors at bunker; all shipping screws removed and tested the operation - all okay
|
FIR01-00547
| INSP-Sprinkler Rough-in | 11/2/2001 | 11/5/2001 | 11/5/2001 12:00:00 AM | P | PART |
|
|
fire --nate- ###-#### okay to cover between col 3-4 only. 11/5/2001 2:28:41 PM
|
FIR00-00405
| INSP-Sprinkler Rough-in/Hydro | 11/5/2001 | 11/5/2001 | 11/5/2001 12:00:00 AM | P | PART |
|
|
###-#### RICK okay on hydro for stanpipe and pump areas only 11/5/2001 2:29:11 PM
|
FIR01-00515
| INSP-Sprinkler Rough-in/Hydro | 11/5/2001 | 11/5/2001 | 11/5/2001 12:00:00 AM | P | PART |
|
|
###-#### mike FDC hydro okay; partial r/i okay - need heads and drops installed 11/5/2001 3:37:22 PM
|