Inspections for the day of: Friday, November 5, 2004.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD04-01510 BLD-Aging Inspection11/5/200411/5/200411/5/2004 12:00:00 AM DONE
I spoke to the contractor, chris, and he was going to call the electrical contractor to get the status on the emergency lights and then call me back 11/5/2004 9:29:25 AM
BLD04-02254 FIRE-Final Inspection11/4/200411/5/200411/5/2004 12:00:00 AMAFAIL
I notified the tenant improvement contractor, Gary, that I could not give him a final on the tenant improvement since the shell pemit had never been finaled and was infact expired. After discussing this with Linda and George Slane I told him he needs to contact plan review on reinstating the permit 11/5/2004 10:25:12 AM
BLD02-03023 BLD-Conference11/5/200411/5/200411/5/2004 12:00:00 AMADONE
I notified the tenant improvement contractor, Gary, that I could not give him a final on the tenant improvement since the shell pemit had never been finaled and was infact expired. After discussing this with Linda and George Slane I told him he needs to contact plan review on reinstating the permit
FIR04-00236 INSP-Sprinkler Rough-in/Hydro11/5/200411/5/200411/5/2004 12:00:00 AMPPART
Overhead hydro test passed. Forward flush of backflow passed. 24 hour air test started at 2:30 with 41 1/2 psi on the guage. 11/5/2004 2:41:03 PM
FIR04-00549 INSP-Final Inspection11/3/200411/5/200411/5/2004 12:00:00 AMPFAIL
Sprinkler rough-in is ok. Piping is ok to cover. Can't final until ceilings are complete at sprinkler pendants. 11/4/2004 11:26:29 AM
BLD04-01268 FIRE-Final Inspection11/5/200411/5/200411/5/2004 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 11/5/2004 at 7:37:33 AM. Contact: ###-####.