Inspections for the day of: Thursday, November 5, 2009.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00473 FIR-Aging Inspection11/5/200911/5/200911/5/2009 4:39:16 PM DEFR
Work in progress.
FIR09-00384 INSP-Sprinkler Rough-in11/5/200911/5/200911/5/2009 4:38:21 PMPPART
Partial overhead cover approved as discussed.
BLD08-02268 FIRE-Final Inspection11/5/200911/5/200911/5/2009 4:37:33 PMPPASS
Fire life safety finaled.
FIR09-00264 INSP-Final Inspection11/4/200911/5/200911/5/2009 4:37:00 PMPPASS
On site functional trip testing of the new dry system completed satisfactory, water delivered to the inspectors test at 60 seconds. Final walkthrough passed, permit finaled.
BLD09-01427 FIRE-Final Inspection11/5/200911/5/200911/5/2009 4:33:54 PMPNR
Project related fire sprinkler permit work must be finaled prior to building life safety approvals.
FIR09-00627 INSP-Sprinkler Rough-in/Hydro11/5/200911/5/200911/5/2009 4:32:57 PMPPART
Okay to cover ceiling at the new medical gas closet.
FIR06-00726 INSP-Final Inspection11/4/200911/5/200911/5/2009 4:32:05 PMAPASS
Scope of fire sprinkler permit work approved for final status.
FIR09-00503 INSP-Final Inspection11/2/200911/5/200911/5/2009 4:31:24 PMAPART
Items needed for final include knox box installation, post signage at the door to the room containing the FACP, provide a lock at the circut breaker to the panel, post a map at the panel indicating locations of initiating devices and addresses/zones, one duct detector (#2) needs to be retested for unit shutdown as HVAC controls could not be initiated. See fire code review notes items # 21,22 and 23. Remainder of fire alarm work passed inspection and site testing.