Inspections for the day of: Monday, November 5, 2012.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR12-00548 INSP-Final Inspection11/5/201211/5/201211/5/2012 4:01:18 PMPFAIL
Need ceiling tile installed prior to a final sign off.
FIR12-00418 INSP-Sprinkler Rough-in11/1/201211/5/201211/5/2012 3:07:24 PMAFAIL
The first and second floor rough-in passed. There are some concerns that fixtures and possible soffits will be too close the the pendant heads. The third floor piping has alot of extra 90's in the piping including in the remote area. The pipe sizing does not match the plans either. I also noted that the tenting is not adequate in several areas. First and second floor piping only can be covered. Third floor piping needs to be resubmitted for review.
BLD12-01243 FIRE-Final Inspection11/5/201211/5/201211/5/2012 3:04:10 PMPFAIL
Remove the two deadbolts and one thumbturn lock from the rear door. Remove the round knob from the rear door and provide single action lever hardware. Mount the fire extinguisher as discussed. Cover the electrical outlets.
FIR12-00418 INSP-Sprinkler Rough-in/Hydro11/1/201211/5/201211/5/2012 1:41:48 PMAPASS
Overhead hydro test passed.
FIR12-00417 INSP-Sprinkler Rough-in/Hydro11/1/201211/5/201211/5/2012 1:41:03 PMAPASS
Overhead hydro test passed.
BLD12-02759 FIRE-Final Inspection11/2/201211/5/201211/5/2012 8:35:55 AMAPASS
Life safety passed.