FIR12-00548
| INSP-Final Inspection | 11/5/2012 | 11/5/2012 | 11/5/2012 4:01:18 PM | P | FAIL |
|
|
Need ceiling tile installed prior to a final sign off.
|
FIR12-00418
| INSP-Sprinkler Rough-in | 11/1/2012 | 11/5/2012 | 11/5/2012 3:07:24 PM | A | FAIL |
|
|
The first and second floor rough-in passed. There are some concerns that fixtures and possible soffits will be too close the the pendant heads. The third floor piping has alot of extra 90's in the piping including in the remote area. The pipe sizing does not match the plans either. I also noted that the tenting is not adequate in several areas. First and second floor piping only can be covered. Third floor piping needs to be resubmitted for review.
|
BLD12-01243
| FIRE-Final Inspection | 11/5/2012 | 11/5/2012 | 11/5/2012 3:04:10 PM | P | FAIL |
|
|
Remove the two deadbolts and one thumbturn lock from the rear door. Remove the round knob from the rear door and provide single action lever hardware. Mount the fire extinguisher as discussed. Cover the electrical outlets.
|
FIR12-00418
| INSP-Sprinkler Rough-in/Hydro | 11/1/2012 | 11/5/2012 | 11/5/2012 1:41:48 PM | A | PASS |
|
|
Overhead hydro test passed.
|
FIR12-00417
| INSP-Sprinkler Rough-in/Hydro | 11/1/2012 | 11/5/2012 | 11/5/2012 1:41:03 PM | A | PASS |
|
|
Overhead hydro test passed.
|
BLD12-02759
| FIRE-Final Inspection | 11/2/2012 | 11/5/2012 | 11/5/2012 8:35:55 AM | A | PASS |
|
|
Life safety passed.
|