Inspections for the day of: Tuesday, November 5, 2013.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD12-01991 BLD-Final11/1/201311/5/201311/6/2013 6:42:08 AMAPART
Shell and Core Restroom Inspection Levels 1-10, Shell and Core Permit work. Jamal is requesting this for 10:30 AM. Phone #: ###-#### >> Inspection requested via web by Adam Johnson floors 1and 2 ok 6 thru 9 ada stalls only 59 inchs wide
BLD13-00904 BLD-Framing/Rough-in11/4/201311/5/201311/6/2013 6:39:52 AMAPART
Framing Inspection at 17th Floor, Zions. Per Roger Wilson. THanks, Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to insluate and cover north and west outer walls
BLD13-01686 BLD-Conference11/4/201311/5/201311/6/2013 6:38:11 AMPDONE
Conference and slab re-bar inspection. Phone #: ###-#### >> Inspection requested via web by Todd McLean
BLD13-02619 BLD-Foundation11/5/201311/5/201311/6/2013 6:37:33 AMPPASS
Wes Phone #: ###-####
BLD13-01332 BLD-Framing/Rough-in10/30/201311/5/201311/5/2013 4:09:42 PMPPASS
Tim Phone #: ###-####
BLD13-02756 BLD-Foundation11/4/201311/5/201311/5/2013 2:16:39 PMAPASS
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD13-01782 BLD-Conference11/4/201311/5/201311/5/2013 2:14:24 PMAPASS
15th Floor Framing inspection, request for cover via Murph. Thanks. Adam ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD12-01991 BLD-Framing/Rough-in11/1/201311/5/201311/5/2013 2:12:49 PMAFAIL
Wall perimeter inspection at 9th and 10th floor, exterior walls, core and shell scope of work, conformation of cover. Requesting in conjunction with 10:30 inspection of Shell and Core restrooms. Thanks. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD13-01956 BLD-Final11/5/201311/5/201311/5/2013 2:09:43 PMPPASS
Jenny Phone #: ###-####
BLD13-02782 BLD-Footing11/5/201311/5/201311/5/2013 1:17:10 PMPPASS
brian Phone #: ###-####
BLD13-02128 BLD-Framing/Rough-in11/4/201311/5/201311/5/2013 9:27:58 AMAPASS
steve Phone #: ###-####
BLD13-02426 BLD-Framing/Rough-in11/4/201311/5/201311/5/2013 9:27:17 AMAPASS
Rollo--Shear inspection Phone #: ###-#### hold downs are installed ok to cover
BLD13-02756 BLD-Foundation11/1/201311/5/201311/4/2013 2:40:41 PMPCANC
Phone #: 2086971241 >> Inspection requested via mobile web by Heron Inspection cancelled via mobile web on Monday, November 04, 2013.