ESC13-01045
| Site Preparation | 11/5/2013 | 11/5/2013 | 11/5/2013 1:15:13 PM | P | FAIL |
|
|
Violations observed:
1. Work started prior to site prep inspection 2. No BMPs implemented 3. Trackout onto street 4. No ESC permit posted
SWO- stop work order in effect until following corrections are complete:
1. Sweep sidewalks road with trackout 2. Provide construction entrances 3. Install wattles at borders with sidewalk/driveway 4. Post ESC permit 5. Call in for re-inspection
|
ESC13-00986
| Site Preparation | 11/5/2013 | 11/5/2013 | 11/5/2013 1:12:45 PM | P | FAIL |
|
|
Violations observed:
1. Work started prior to site prep inspection 2. No BMPs implemented 3. Trackout onto street 4. No ESC permit posted
SWO- stop work order in effect until following corrections are complete:
1. Sweep sidewalks road with trackout 2. Provide construction entrances 3. Install wattles at borders with sidewalk/driveway 4. Post ESC permit 5. Call in for re-inspection
|
ESC13-00655
| General Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 12:25:53 PM | | PASS |
|
|
Finaled.
|
ESC13-00655
| DOC - Permit Finaled | 11/5/2013 | 11/5/2013 | 11/5/2013 12:24:55 PM | P | CANC |
|
|
4 plex complete, 11.25 acre site development still in progress with additional phases planned.
|
ESC12-00920
| Aging Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 12:11:35 PM | | PASS |
|
|
ESC permit posted; no construction activity. BLD permit has expired. No corrections at this time.
|
ESC13-00625
| General Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 11:01:09 AM | | PASS |
|
|
Exterior construction is mostly complete. Not yet stabilized. No track out or other ESC violations observed at time of inspection.
|
ESC13-00623
| General Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 10:53:02 AM | | PASS |
|
|
Roof is being framed. No ESC violations observed.
|
ESC13-00665
| General Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 10:49:51 AM | | PASS |
|
|
WIP. No corrections required at this time. Permit posted, no track out, site is well maintained.
|
ESC13-00569
| General Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 10:39:46 AM | | PASS |
|
|
Finaled.
|
ESC13-00569
| DOC - Permit Finaled | 11/5/2013 | 11/5/2013 | 11/5/2013 10:38:14 AM | P | PASS |
|
|
Kiosk is installed and surrounding area is stabilized and landscaped. ESC conditions have been met, no further ESC inspections required.
|
ESC13-01012
| Site Preparation | 11/4/2013 | 11/5/2013 | 11/5/2013 10:26:52 AM | A | PART |
|
|
Kristy Phone #: ###-####
No ESC violations or track out, but some earth work has already begun. Called Wood Bros contact Kristy and warned that future site prep inspections must not have already started or will be stopped. Approved to continue.
|
ESC12-01142
| Aging Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 10:14:56 AM | | PASS |
|
|
WIP. BMPs are installed properly. No corrections at this time.
|
ESC12-01144
| Aging Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 9:56:14 AM | | PASS |
|
|
Finaled.
|
ESC12-01144
| DOC - Permit Finaled | 11/5/2013 | 11/5/2013 | 11/5/2013 9:56:00 AM | P | PASS |
|
|
Permits finaled. House complete and occupied. ESC conditions met.
|
ESC13-00991
| Site Preparation | 11/4/2013 | 11/5/2013 | 11/5/2013 9:51:00 AM | A | PASS |
|
|
rollo Phone #: ###-####
Site is ready for excavation. Adjacent lots already built on and stabilized. Subdivision BMPs in place.
|
ESC13-01013
| Site Preparation | 11/4/2013 | 11/5/2013 | 11/5/2013 9:47:31 AM | A | PASS |
|
|
Clint Phone #: ###-####
Had meeting with RP Clint. Homesite is ready for excavation. Permit posted, drop inlet protection provided, and concrete washout. Wattles to be installed along Wolf Tree at downslope end of block. Approved.
|
ESC13-00984
| Site Preparation | 11/4/2013 | 11/5/2013 | 11/5/2013 9:47:07 AM | A | PASS |
|
|
Clint Phone #: ###-####
Had meeting with RP Clint. Homesite is ready for excavation. Permit posted, drop inlet protection provided, and concrete washout. Wattles to be installed along Wolf Tree at downslope end of block. Approved.
|