GCB13-00146
| GCB-Footing | 11/6/2013 | 11/6/2013 | 11/7/2013 6:21:44 AM | P | PASS |
|
|
Nate ###-#### Concrete pour at 4:00, please inspect footings prior
|
BLD13-01451
| BLD-Final | 11/5/2013 | 11/6/2013 | 11/7/2013 6:21:18 AM | P | PASS |
|
|
Justin Phone #: ###-#### ok for perm occ
|
BLD13-01633
| BLD-Framing/Rough-in | 11/6/2013 | 11/6/2013 | 11/7/2013 6:20:22 AM | P | PART |
|
|
Framing inspection of Ruths Chris, 8th and Main 1st Floor, Mike Beeson, Thanks. ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover walls servce area
|
BLD13-02650
| BLD-Footing | 11/6/2013 | 11/6/2013 | 11/7/2013 6:18:54 AM | P | PASS |
|
|
wes Phone #: ###-####
|
BLD13-02817
| BLD-Final | 11/5/2013 | 11/6/2013 | 11/6/2013 11:19:50 AM | A | FAIL |
|
|
Mike Phone #: ###-#### needs fire rated glass in side light
|
BLD13-01215
| BLD-Ceiling Grid Inspection | 11/5/2013 | 11/6/2013 | 11/6/2013 11:18:37 AM | A | PASS |
|
|
Larry Phone #: ###-####
|
BLD12-01528
| BLD-Ceiling Grid Inspection | 11/5/2013 | 11/6/2013 | 11/6/2013 11:18:14 AM | A | PASS |
|
|
Daryl Phone #: ###-####
|
BLD13-00672
| BLD-Other | 11/5/2013 | 11/6/2013 | 11/6/2013 11:17:46 AM | A | PART |
|
|
Partial roofing to allow felt paper installation - Heather Phone #: ###-#### ok to cover
|
BLD13-01729
| BLD-Energy code compliance | 11/4/2013 | 11/6/2013 | 11/6/2013 9:20:56 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD13-01751
| BLD-Wall Bracing | 11/5/2013 | 11/6/2013 | 11/6/2013 9:20:25 AM | A | PASS |
|
|
matt Phone #: ###-####
|
BLD13-02854
| BLD-Framing/Rough-in | 11/1/2013 | 11/6/2013 | 11/6/2013 12:00:00 AM | A | CANC |
|
|
late morning - Don Phone #: ###-#### 11-6-13 per Donald May cancel this inspection not ready
|