FIR13-00488
| INSP-Final Inspection | 11/4/2013 | 11/6/2013 | 11/6/2013 3:41:22 PM | P | PASS |
|
|
Permit finaled
|
BLD13-01319
| FIRE-Final Inspection | 11/6/2013 | 11/6/2013 | 11/6/2013 3:26:06 PM | P | PASS |
|
|
Life safety passed
|
FIR13-00370
| INSP-Final Inspection | 11/1/2013 | 11/6/2013 | 11/6/2013 3:25:31 PM | P | PASS |
|
|
Permit finaled
|
FIR13-00343
| INSP-Final Inspection | 11/4/2013 | 11/6/2013 | 11/6/2013 3:25:04 PM | A | PASS |
|
|
Permit finaled
|
FIR12-00717
| INSP-Sprinkler Rough-in | 11/5/2013 | 11/6/2013 | 11/6/2013 10:42:24 AM | A | PASS |
|
|
See the city approved plans for location dated with todays date where sprinkler piping is ok to cover. Also the north east portion of the new gridded system passed hydro test.
|
FIR13-00442
| INSP-Final Inspection | 11/5/2013 | 11/6/2013 | 11/6/2013 8:35:49 AM | A | PASS |
|
|
permit finaled
|