BLD04-01324
| FIRE-Final Inspection | 11/7/2005 | 11/7/2005 | 11/7/2005 5:15:54 PM | P | PART |
|
|
Final not complete, see correction notice for a list of items.
|
BLD05-00922
| FIRE-Final Inspection | 11/7/2005 | 11/7/2005 | 11/7/2005 5:14:17 PM | P | FAIL |
|
|
Door is not installed yet at box office storage room below escalators, provide fire extinguisher at first floor elevator lobby, repair emergency light at stair landing by theatre #7, temporary max occupant load signs have been installed, door hardware is missing at mezz door, inspection concluded at this time project is not ready for final inspection.
|
FIR05-00372
| INSP-Final Inspection | 11/7/2005 | 11/7/2005 | 11/7/2005 5:08:24 PM | P | FAIL |
|
|
Missing two escutcheons at box office area, two heads at the concession bar are spaced incorrectly, one head in the men's restroom is blocked by a column, head appears overspaced at atrium above east escalators, the inspection was concluded at this time-contractor to walk through project and reschedule inspection when complete.
|
MIS05-00192
| FIR-Final | 11/7/2005 | 11/7/2005 | 11/7/2005 5:01:12 PM | P | FAIL |
|
|
Mount K class extinguisher to the wall as discussed, provide max occupant load sign, verify current annual inspection on the building fire sprinkler system, remove or disable the keyed locking hardware at the main entry/exit door threshold.
|
BLD04-01966
| FIRE-Final Inspection | 11/7/2005 | 11/7/2005 | 11/7/2005 2:54:02 PM | P | PASS |
|
|
Fire life safety is satisfactory.
|
FIR05-00670
| INSP-Final Inspection | 11/4/2005 | 11/7/2005 | 11/7/2005 12:48:36 PM | P | PART |
|
|
Testing is acceptable, however, strobe height is too low in four offices-this was manually adjusted by the contractor on site due to the large wall opening- devices must be secured and wall repaired prior to final approval to meet min. height requirements for the strobe lens.
|
BLD05-02432
| FIRE-Sprinkler Rough-in | 11/7/2005 | 11/7/2005 | 11/7/2005 11:25:40 AM | P | CANC |
|
|
Wrong inspection type called in by the general contractor, was intended for the sprinkler permit.
|
MIS05-00203
| FIR-Final | 11/4/2005 | 11/7/2005 | 11/7/2005 11:21:03 AM | A | FAIL |
|
|
Provide approved door hardware at the main entry/exit door as discussed, provide one fire extinguisher with current inspection tag mounted along a normal path of travel.
|
FIR05-00726
| INSP-Sprinkler Rough-in | 11/4/2005 | 11/7/2005 | 11/7/2005 10:31:03 AM | A | FAIL |
|
|
Attatch retaining strap at beam clamp on arm-over hanger, heads within one foot of heat diffusers must be intermediate temperature, heads in the drop ceiling areas are not cut in at this time.
|