Inspections for the day of: Monday, November 7, 2005.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAimee Hughes
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC05-01464 Tracking Control11/7/200511/7/200511/7/2005 2:40:19 PMPPASS
Site looks fine.
ESC05-00209 Tracking Control11/7/200511/7/200511/7/2005 2:39:53 PMPPASS
Site looks fine.
ESC05-00808 Tracking Control11/7/200511/7/200511/7/2005 2:39:23 PMPPASS
Site looks fine.
ESC05-01631 Tracking Control11/7/200511/7/200511/7/2005 2:38:59 PMPPASS
Site looks fine.
ESC05-01103 Tracking Control11/7/200511/7/200511/7/2005 2:38:15 PMPPASS
Site looks fine.
ESC04-01305 Tracking Control11/7/200511/7/200511/7/2005 2:37:32 PMPPART
verbal c/n to RP about watching trackout off of sites.
ESC05-00485 Tracking Control10/24/200511/7/200511/7/2005 2:36:22 PMAPASS
Site looks fine.
ESC05-01438 Tracking Control11/7/200511/7/200511/7/2005 2:25:18 PMPPART
verbal c/n to RP about watching trackout off of site and installing delivery pad for materials.
ESC05-00718 Tracking Control10/24/200511/7/200511/7/2005 2:16:05 PMAPASS
Site looks good.
ESC05-01150 Tracking Control10/17/200511/7/200511/7/2005 9:54:52 AMAPASS
Site looks fine. Talked to RP about moving signage back to the front of the site.
ESC05-00281 Tracking Control10/17/200511/7/200511/7/2005 9:46:27 AMAFAIL
verbal c/n to RP. d/i protection in parking lot needs to be maintained and trackout from both entrances needs to be cleaned up and maintained.
ESC04-00262 Tracking Control10/17/200511/7/200511/7/2005 9:42:03 AMAPASS
Site looks fine. Talked to RP about final stabilization schedule. Landscaping should be completed by the end of the week.