BLD17-01089
| BLD-Final | 11/7/2017 | 11/7/2017 | 11/7/2017 4:18:15 PM | P | PASS |
|
|
Jose Phone #: ###-#### OK for Perm Occ.
|
BLD17-03123
| BLD-Framing/Rough-in | 11/3/2017 | 11/7/2017 | 11/7/2017 3:48:56 PM | P | PASS |
|
|
Brandi ext 211 Phone #: ###-####
|
BLD16-04077
| BLD-Energy code compliance | 11/7/2017 | 11/7/2017 | 11/7/2017 3:06:51 PM | P | PASS |
|
|
Exterior walls foam insulation in the Admin Bldg. Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD17-00874
| BLD-Wall Bracing | 11/7/2017 | 11/7/2017 | 11/7/2017 1:30:52 PM | P | PASS |
|
|
Gary-later if possible Phone #: ###-####
|
BLD17-04039
| BLD-Other | 11/6/2017 | 11/7/2017 | 11/7/2017 1:01:00 PM | P | PART |
|
|
roof decking insp // Dustin Phone #: ###-#### 90 percent of roof sheathing inspected and OK on East 1/2 of house.
|
BLD17-02963
| BLD-Final | 11/6/2017 | 11/7/2017 | 11/7/2017 12:28:29 PM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Colyn Levandoske Need Mech.
|
BLD17-02475
| BLD-Final | 11/6/2017 | 11/7/2017 | 11/7/2017 12:27:57 PM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Colyn Levandoske Need Mech
|
BLD17-03804
| BLD-Framing/Rough-in | 11/6/2017 | 11/7/2017 | 11/7/2017 10:36:39 AM | A | PASS |
|
|
Ernie Phone #: ###-#### Frame and Energy ....Pass.
|
MIS17-00066
| BLD-Conference | 11/2/2017 | 11/7/2017 | 11/7/2017 10:16:19 AM | A | DONE |
|
|
Check back.........No change since prior inspection.
|
BLD17-03760
| BLD-Final | 11/6/2017 | 11/7/2017 | 11/7/2017 9:54:13 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Cindy Zickgraf
|
BLD17-03760
| DOC - Permit Finaled | 11/7/2017 | 11/7/2017 | 11/7/2017 9:53:59 AM | P | PASS |
|
|
No one at home....can see majority of roof.........Appears to be done and OK.
|