MIS17-00375
| ELE-Conference | 11/7/2017 | 11/7/2017 | 11/15/2017 7:22:09 AM | P | DONE |
|
|
owner hired electrical contractor to complete work.
|
ELE17-01337
| Conference | 11/7/2017 | 11/7/2017 | 11/7/2017 11:18:20 AM | A | DONE |
|
|
Responded to complaint through DBS. Spoke with Rick Bagley and David Banks (Superintendent) rain water getting in west half of building, floors 2,3,4,5 Hold on West half of building untill dried in and roofing completed and inspected.
|
ELE11-02061
| ELE-Aging Inspection | 11/7/2017 | 11/7/2017 | 11/7/2017 11:11:58 AM | | DONE |
|
|
Spoke with contractor, gave reminder notice of needed final inspection
|
ELE11-01720
| ELE-Aging Inspection | 11/7/2017 | 11/7/2017 | 11/7/2017 11:11:11 AM | | DONE |
|
|
Spoke with contractor, gave reminder notice of needed final inspection
|
ELE13-02192
| ELE-Aging Inspection | 11/7/2017 | 11/7/2017 | 11/7/2017 10:18:39 AM | | DONE |
|
|
see final
|
ELE13-02192
| Final | 11/7/2017 | 11/7/2017 | 11/7/2017 10:18:22 AM | P | PASS |
|
|
Switches and receptacles replaced, job complete. Contractor no longer available
|
ELE17-03697
| Final | 11/6/2017 | 11/7/2017 | 11/7/2017 10:09:03 AM | A | PASS |
|
|
Carl Phone #: ###-#### Job complete, power connected after hours. Final ok
|