PLM99-02795
| Plumbing Rough-in | 11/7/1999 | 11/8/1999 | 11/8/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/07/1999 at 17:48:28. Contact: ###-####. Final ok
|
PLM99-03688
| Plumbing Rough-in | 11/8/1999 | 11/8/1999 | 11/8/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/08/1999 at 06:35:50. Contact: ###-####. R/I ok
|
PLM99-02795
| Final | 11/8/1999 | 11/8/1999 | 11/8/1999 12:00:00 AM | A | PASS |
|
|
final ok
|
PLM99-02936
| Plumbing Rough-in | 11/8/1999 | 11/8/1999 | 11/8/1999 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 11/08/1999 at 08:15:47. Contact: ###-####. Needs testing.
|
PLM99-03724
| Plumbing Rough-in | 11/8/1999 | 11/8/1999 | 11/8/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 11/08/1999 at 08:23:12. Contact: ###-####. R/I ok
|
PLM99-03742
| Plumbing Rough-in | 11/8/1999 | 11/8/1999 | 11/8/1999 12:00:00 AM | P | PASS |
|
|
GATES PLUMBING ###-#### RE-INSP R/I R/I ok
|
PLM99-03767
| Plumbing Rough-in | 11/8/1999 | 11/8/1999 | 11/8/1999 12:00:00 AM | P | PART |
|
|
SHELBY ###-#### R/I G/W ok
|
PLM99-03766
| Plumbing Rough-in | 11/8/1999 | 11/8/1999 | 11/8/1999 12:00:00 AM | P | PASS |
|
|
AMY-- ###-#### R/I R/I ok
|