ELE12-00762
| ELE-Aging Inspection | 11/8/2013 | 11/8/2013 | 11/8/2013 4:21:56 PM | | DONE |
|
|
Waiting on owner
|
ELE12-00804
| ELE-Aging Inspection | 11/8/2013 | 11/8/2013 | 11/8/2013 4:01:40 PM | | DONE |
|
|
Waiting on owner
|
ELE13-02874
| Electrical Rough-In | 11/6/2013 | 11/8/2013 | 11/8/2013 3:46:53 PM | P | PASS |
|
|
Don Phone #: ###-#### wall and ceiling rough in ok cover
|
ELE13-02057
| Electrical Rough-In | 11/8/2013 | 11/8/2013 | 11/8/2013 3:02:00 PM | P | PASS |
|
|
Trench back fill. Phone #: ###-#### >> Inspection requested via web by Buster Bowen Fire pump underground west and north rough in ok cover
|
ELE13-02469
| Electrical Rough-In | 11/8/2013 | 11/8/2013 | 11/8/2013 2:21:12 PM | P | PASS |
|
|
###-#### all walls complete. Rough in ok cover
|
ELE13-03133
| Electrical Rough-In | 11/7/2013 | 11/8/2013 | 11/8/2013 1:37:07 PM | P | PASS |
|
|
turn on haines off of warm springs. go to hays and turn right. on the left side of the road up hill. Phone #: ###-#### >> Inspection requested via web by Brian Hughes Rough in ok cover
|
ELE13-02968
| Electrical Rough-In | 11/8/2013 | 11/8/2013 | 11/8/2013 1:24:21 PM | P | PASS |
|
|
This rough in is ONLY for a heated tile floor in the master bathroom. Phone #: ###-#### >> Inspection requested via web by Rhonda Zamagni Floor heat box and raceway rough in ok cover
|
ELE13-03133
| Permanent Service | 11/8/2013 | 11/8/2013 | 11/8/2013 1:24:10 PM | P | PASS |
|
|
turn on haines off of warm springs. go to hays and turn right. on the left side of the road up hill. Phone #: ###-#### >> Inspection requested via web by Brian Hughes p/s o/h n ok
|
ELE13-03124
| Electrical Rough-In | 11/7/2013 | 11/8/2013 | 11/8/2013 12:54:01 PM | A | PASS |
|
|
Master bed and bath remodel. Phone #: ###-#### >> Inspection requested via web by shane vigil Rough in ok cover
|
ELE13-03128
| Final | 11/8/2013 | 11/8/2013 | 11/8/2013 12:53:21 PM | A | PASS |
|
|
Inspection anytime time today is fine. New surface mount outlet for water feature is on the right side (outside) of house. Thank you! Phone #: ###-#### >> Inspection requested via web by Adam Staigle Final ok
|
ELE13-03128
| Electrical Rough-In | 11/8/2013 | 11/8/2013 | 11/8/2013 12:52:59 PM | P | PASS |
|
|
Inspection anytime time today is fine. New surface mount outlet for water feature is on the right side (outside) of house. Thank you! Phone #: ###-#### >> Inspection requested via web by Adam Staigle Rough in ok
|
ELE13-02791
| Conference | 11/7/2013 | 11/8/2013 | 11/8/2013 10:19:31 AM | A | DONE |
|
|
Requesting a consultation for the Woodland Empire project. Call Rod Tomlinson with any questions. Phone #: ###-#### >> Inspection requested via web by Clint Tate Discussed overhead service riser clearance over alley and location of disconnecting means. Water pipe feeding building is non metallic.
|
ELE12-01694
| Final | 11/7/2013 | 11/8/2013 | 11/8/2013 9:44:05 AM | A | FAIL |
|
|
Jason Timmons (contractor) will meet you there. It is just an inspection on the kitchen. Phone #: ###-#### >> Inspection requested via web by Craig Korell 110.3- Installation not complete. Bare NM cable hanging for light in entry. 2 receptical outlets not working in nook and breaker blanks needed.
|
ELE13-02011
| Final | 11/8/2013 | 11/8/2013 | 11/8/2013 9:23:57 AM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Heath Thomas Contractor stated pancake box used on out front entry light. Final ok
|
ELE13-03070
| Final | 11/7/2013 | 11/8/2013 | 11/8/2013 9:12:43 AM | A | FAIL |
|
|
Phone #: ###-#### >> Inspection requested via web by steve ragan 250.24- The grounding electrode conductor shall terminate at the same terminal or bus bar as the grounded conductor
|
GCE13-00066
| GCE-Final | 11/7/2013 | 11/8/2013 | 11/8/2013 8:59:09 AM | A | PASS |
|
|
Tim ###-#### Final ok
|
GCE13-00185
| GCE-Final | 11/7/2013 | 11/8/2013 | 11/8/2013 8:40:03 AM | A | PASS |
|
|
Robert ###-#### Heat pump final ok
|