Inspections for the day of: Friday, November 8, 2013.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR13-00571 INSP-Sprinkler Rough-in11/7/201311/8/201311/8/2013 3:41:48 PMPPASS
Rough-in passed. Piping is ok to cover.
FIR13-00441 INSP-Final Inspection11/7/201311/8/201311/8/2013 3:37:51 PMPFAIL
Tyco heads have been installed instead of the submitted Viking, provide one additional brace at the end of the 4" main and provide letter from manufacturer to support the installation of the hangers from the bottom of the z purlins.
BLD13-00440 FIRE-Final Inspection11/7/201311/8/201311/8/2013 2:32:20 PMPPASS
Life safety passed
FIR13-00584 INSP-Final Inspection11/7/201311/8/201311/8/2013 2:30:07 PMPPASS
Permit finaled
FIR13-00598 INSP-Final Inspection11/8/201311/8/201311/8/2013 1:39:26 PMPPASS
Permit finaled
BLD13-01578 FIRE-Final Inspection11/7/201311/8/201311/8/2013 1:37:36 PMAPASS
Life safety passed
BLD13-02948 FIRE-Final Inspection11/7/201311/8/201311/8/2013 12:39:04 PMAFAIL
I let Nate know that per Jason Blais the exit sign/emergency lights, hardware at the new double doors and the exterior stairs would need to be completed prior to a temporary occupancy approval for the warehouse area could be given. Phone #: ###-####
FIR13-00617 INSP-Final Inspection11/7/201311/8/201311/8/2013 11:44:46 AMAPASS
Permit finaled
FIR08-00550 INSP-Final Inspection11/7/201311/8/201311/8/2013 11:27:27 AMAFAIL
Began inspection by verifying the sync of the audio/visual devices. When testing the horns on most of the first floor and the west half of the second floor failed to work. Inspection stopped and no devices tested.
BLD13-01024 FIRE-Final Inspection11/7/201311/8/201311/8/2013 9:20:31 AMAPASS
life safety passed
FIR13-00581 INSP-Final Inspection11/1/201311/8/201311/8/2013 8:37:24 AMACANC
tim will reschedule this for next week since he can't make it there when I can be there
FIR13-00596 INSP-Final Inspection11/7/201311/8/201311/8/2013 8:36:15 AMAPASS
Permit finaled
FIR13-00576 INSP-Conference11/7/201311/8/201311/8/2013 7:43:13 AMADONE
Construction at front entry has changed to combustible. I agreed that a single upright head and as-builts showing this addition would suffice. I noted that four way bracing will be required at the top of the main piping at the risers above the restrooms.