Inspections for the day of: Tuesday, November 8, 2016.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00712 INSP-Sprinkler Rough-in11/8/201611/8/201611/8/2016 2:52:55 PMPPASS
Todays inspection was just for the IBR which is approved for cover. I let the general contractor know that it appears to barely meet he minimum 4'-6" bury depth and that the remaining piping would be better buried alittle deeper. He agreed.
FIR16-00692 INSP-Sprinkler Rough-in11/8/201611/8/201611/8/2016 1:49:55 PMPCANC
Supply line cover passed
FIR16-00693 INSP-Sprinkler Rough-in11/8/201611/8/201611/8/2016 1:49:42 PMPPASS
Supply line cover passed
BLD16-01662 FIRE-Final Inspection11/8/201611/8/201611/8/2016 1:49:16 PMPFAIL
Provide fire dept approval of the operation of the Opticon system at the main entry gate. All other items appear ok.
BLD16-01665 FIRE-Final Inspection11/8/201611/8/201611/8/2016 1:35:32 PMPFAIL
Provide fire dept approval of the operation of the Opticon system at the main entry gate. All other items appear ok.
BLD16-01663 FIRE-Final Inspection11/8/201611/8/201611/8/2016 1:35:14 PMPFAIL
Provide fire dept approval of the operation of the Opticon system at the main entry gate. All other items appear ok.
BLD16-01664 FIRE-Final Inspection11/8/201611/8/201611/8/2016 1:34:49 PMPFAIL
Provide fire dept approval of the operation of the Opticon system at the main entry gate. All other items appear ok.
BLD16-01660 FIRE-Final Inspection11/8/201611/8/201611/8/2016 1:34:24 PMPFAIL
Provide fire dept approval of the operation of the Opticon system at the main entry gate. All other items appear ok.
BLD16-01661 FIRE-Final Inspection11/8/201611/8/201611/8/2016 1:33:48 PMPFAIL
Provide fire dept approval of the operation of the Opticon system at the main entry gate, provide fire extinguishers, exit signs, emergency lighting and exit discharge lighting as per the city approved plans.
FIR16-00547 INSP-Final Inspection11/7/201611/8/201611/8/2016 12:50:55 PMPCANC
To be canceled per Dave Phone #: ###-####
FIR16-00101 INSP-Sprinkler Rough-in11/7/201611/8/201611/8/2016 9:19:07 AMPCANC
Tyler Miller is the contact for this inspection. He needs a rough to cover inspection of 3 units on the 4th floor. Thank you
Phone #: ###-#### Inspection requested via web by Stan Beus
BLD16-01367 FIRE-Final Inspection11/7/201611/8/201611/8/2016 8:44:53 AMAFAIL
Repair emergency light in corridor, provide tagged and mounted fire extinguisher, remove storage in the back corridor that blocks the exit.
FIR16-00453 INSP-Alarm Testing11/7/201611/8/201611/8/2016 7:58:52 AMAFAIL
Store employee did not show up at the agreed time to allow access to the store. No inspection performed.


We will be ready for our inspection at 7:30am per our conversation on Friday the 4th. Barney Sanders will make sure all RTU''s are running.

Thank you, Phone #: ###-#### Inspection requested via web by Josiah Monett